Prompt Progress Payment to Subconsultants Clause Samples

Prompt Progress Payment to Subconsultants. If this AGREEMENT is subject to Section 7108.5 of the Business and Professions Code concerning prompt payment to subcontractors, CONSULTANT agrees that not later than seven (7) calendar days after receipt of payment from ALAMEDA CTC, CONSULTANT shall pay to its subconsultants all amounts due from such payment, unless otherwise agreed to in writing. In any event, whether or not Section 7108.5 is applicable, CONSULTANT shall pay its subconsultants all amounts due within the ten (10)-day period set forth in Article I, Section A, Paragraph 4. Any delay or postponement of payment over thirty (30) calendar days may take place only for good cause and with ALAMEDA CTC’s prior written approval. Any violation of Section 7108.5 shall subject the violating CONSULTANT or subconsultants to the penalties, sanctions, and other remedies of that Section. This requirement shall not be construed to limit or impair any contractual, administrative, or judicial remedies, otherwise available to the CONSULTANT or subconsultant in the event of a dispute involving late payment or nonpayment by the CONSULTANT, deficient subconsultant performance, and/or noncompliance by a subconsultant. This clause applies to both DBE and non-DBE subconsultants.
Prompt Progress Payment to Subconsultants. If this AGREEMENT is subject to Section 7108.5 of the Business and Professions Code concerning prompt payment to subcontractors, CONSULTANT agrees that not later than seven (7) calendar days after receipt of payment from ALAMEDA CTC, CONSULTANT shall pay to its subconsultants all amounts due from such payment, unless otherwise agreed to in writing. In any event, whether or not Section 7108.5 is applicable, CONSULTANT shall pay its subconsultants all amounts due within the fifteen (15)-day period set forth in Article I, Section A, Paragraph 4. Any delay or postponement of payment over thirty
Prompt Progress Payment to Subconsultants. FED ONLY A prime contractor or subcontractor shall pay to any subcontractor not later than 7-days of receipt of each progress payment, in accordance with the provision in Section 7108.5 of the California Business and Professions Code concerning prompt payment to subcontractors. The 7-day rule is applicable unless a longer period is agreed to in writing. Any delay or postponement of payment over 30-days may take place only for good cause and with the COMMISSION's prior written approval. Any violation of Section 7108.5 shall subject the violating contractor or subcontractor to the penalties, sanctions, and other remedies of that Section. This requirement shall not be construed to limit or impair any contractual, administrative, or judicial remedies, otherwise available to the contractor or subcontractor in the event of a dispute involving late payment or nonpayment by the contractor, deficient subcontractor performance, and/or noncompliance by a subcontractor. This clause applies to both DBE and non-DBE subcontractors.
Prompt Progress Payment to Subconsultants. TAMC requires Consultant to pay any subconsultants within fifteen (15) days after receiving each progress payment. Any delay or postponement of payment may take place only for good cause and with TAMC’s prior written approval. Any violation of these provisions shall subject the violating Consultant to the penalties, sanctions and remedies specified in Section 3321 of the California Civil Code (CCC). This requirement shall not be construed to limit or impair any contractual, administrative, or judicial remedies, otherwise available to Consultant or subconsultant in the event of a dispute involving late payment or nonpayment by Consultant, deficient subconsultant performance, and/or noncompliance by a subconsultant. This clause applies to both DBE and non-DBE subconsultants.

Related to Prompt Progress Payment to Subconsultants

  • Prompt Payment to Subcontractors (a) Within 7 days of receipt by the Contractor of each payment from the City under this contract, the Contractor shall pay all Subcontractors (which term includes subconsultants and suppliers) based on work completed or service provided under the subcontract. Should any payment to the Subcontractor be delayed by more than 7 days after receipt of payment by the Contractor from the City under this contract, the Contractor shall pay the Subcontractor interest, beginning on the 8th day, at the rate of 1% per month or fraction thereof on such unpaid balance as may be due. By appropriate litigation, Subcontractors shall have the right to enforce this subsection (a) directly against the Contractor, but not against the City of Durham. (b) If the individual assigned to administer this contract for the City (in this section, titled “Prompt Payment to Subcontractors,” he or she will be referred to as the “Project Manager”) determines that it is appropriate to enforce subsection (a) in this manner, the City may withhold from progress or final payments to the Contractor the sums estimated by the Project Manager to be (i) the amount of interest due to the Subcontractor under subsection (a), and/or (ii) the amounts past-due under subsection (a) to the Subcontractor but not exceeding 5% of the payment(s) due from the City to the Contractor. This subsection (b) does not limit any other rights to withhold payments that the City may have. (c) Nothing in this section (titled “Prompt Payment to Subcontractors”) shall prevent the Contractor at the time of invoicing, application, and certification to the City from withholding invoicing, application, and certification to the City for payment to the Subcontractor for unsatisfactory job progress; defective goods, services, or construction not remedied; disputed work; third-party claims filed or reasonable evidence that such a claim will be filed; failure of the subcontractor to make timely payments for labor, equipment, and materials; damage to the Contractor or another subcontractor; reasonable evidence that the subcontract cannot be completed for the unpaid balance of the subcontract sum; or a reasonable amount for retainage not to exceed 10%. (d) The Project Manager may require, as a prerequisite to making progress or final payments, that the Contractor provide statements from any Subcontractors designated by the Project Manager regarding the status of their accounts with the Contractor. The statements shall be in such format as the Project Manager reasonably requires, including notarization if so specified.

  • Payment to Subcontractors (If applicable) As required by Minnesota Statute § 16A.1245, the prime Contractor must pay all subContractors, less any retainage, within 10 calendar days of the prime Contractor’s receipt of payment from the State for undisputed services provided by the subContractor(s) and must pay interest at the rate of one and one-half percent per month or any part of a month to the subContractor(s) on any undisputed amount not paid on time to the subContractor(s).

  • PAYMENT TO SUB-CONTRACTORS 12.1 Transnet reserves the right, in its sole discretion, to make payment directly to the sub-contractor of the Supplier/Service Provider, subject to the following conditions: a) Receipt of an undisputed invoice from the sub-contractor; and b) Receipt of written confirmation from the Supplier/Service Provider that the amounts claimed by the sub-contractor are correct and that the services for which the sub- contractor has requested payment were rendered to the satisfaction of the Supplier/Service Provider, against the required standards. 12.2 Nothing contained in this clause must be interpreted as bestowing on any sub-contractor a right or legitimate expectation to be paid directly by Transnet. Furthermore, this clause does not bestow any right or legitimate expectation on the Supplier/Service provider to demand that Transnet pay its sub-contractor directly. The decision to pay any sub-contractor directly, remains that of Transnet alone.

  • Payments to Subcontractors Develop and implement a procedure for the review, processing and payment of applications by subcontractors for progress and final payments.

  • Indemnification for Expenses of a Party Who is Wholly or Partly Successful Notwithstanding any other provisions of this Agreement except for Section 27, to the extent that Indemnitee was or is, by reason of Indemnitee’s Corporate Status, a party to (or a participant in) and is successful, on the merits or otherwise, in any Proceeding or in defense of any claim, issue or matter therein, in whole or in part, the Company shall, to the fullest extent permitted by applicable law, indemnify, hold harmless and exonerate Indemnitee against all Expenses actually and reasonably incurred by him or her in connection therewith. If Indemnitee is not wholly successful in such Proceeding but is successful, on the merits or otherwise, as to one or more but less than all claims, issues or matters in such Proceeding, the Company shall, to the fullest extent permitted by applicable law, indemnify, hold harmless and exonerate Indemnitee against all Expenses actually and reasonably incurred by him or her or on his or her behalf in connection with each successfully resolved claim, issue or matter. If Indemnitee is not wholly successful in such Proceeding, the Company also shall, to the fullest extent permitted by applicable law, indemnify, hold harmless and exonerate Indemnitee against all Expenses reasonably incurred in connection with a claim, issue or matter related to any claim, issue, or matter on which Indemnitee was successful. For purposes of this Section and without limitation, the termination of any claim, issue or matter in such a Proceeding by dismissal, with or without prejudice, shall be deemed to be a successful result as to such claim, issue or matter.