Common use of Provisional Sums Clause in Contracts

Provisional Sums. a. If a Provisional Sum is set out at Item 12 of the Sub-Contract Particulars the Sub-Contractor must comply with a direction by Total to carry out the work or supply the item to which the Provisional Sum relates. b. A Provisional Sum included in the Sub-Contract will not itself be payable by Total but where pursuant to a direction, any part or the whole of the work or item to which the Provisional Sum relates is carried out or supplied by the Sub- Contractor, the work or item will be priced by Total, and the difference will be added to or deducted from the Sub- Contract Sum. c. The Sub-Contractor acknowledges the Sub-Contract Sum includes an amount for profit and overheads in relation to the Provisional Sums and unless otherwise stated, with respect to the supply of Provisional Sum items, includes the costs of supply, delivery and installation.

Appears in 3 contracts

Sources: Sub Contract Agreement, Sub Contract Agreement, Sub Contract Agreement