Common use of Punch List Work Clause in Contracts

Punch List Work. Notwithstanding achievement of Project Mechanical Completion, Contractor shall remain obligated to complete the Punch List Items in accordance with this Agreement. Contractor shall give Owner written notice at least five (5) Business Days prior to declaring that Project Mechanical Completion has occurred and shall provide on such date a written Punch List. Owner shall be entitled to verify and, if necessary, correct or add to, the list of Punch List Items provided by Contractor. Contractor agrees to update such Punch List from time to time (but not less often than monthly) after Project Mechanical Completion and until Final Completion.

Appears in 3 contracts

Sources: Build Transfer Agreement, Balance of Plant Engineering, Procurement and Construction Agreement, Wind Energy Project Agreement