Common use of Punch List Work Clause in Contracts

Punch List Work. Within five (5) Business Days after Substantial Completion of each phase of the Tenant Improvements, representatives of Landlord, Tenant and Contractor shall inspect the Premises and agree upon a list of Punch List Items. Landlord shall cause Contractor to complete all Punch List Items within thirty (30) days after designation thereof or if such work cannot reasonably be completed within thirty (30) days, as soon thereafter as is reasonably possible provided Contractor commences repair within such thirty (30) day period and diligently pursues completion of the same.

Appears in 3 contracts

Sources: Sublease (Callidus Software Inc), Sublease (Callidus Software Inc), Lease Agreement (Taleo Corp)