Common use of Punch List Clause in Contracts

Punch List. Developer shall notify the Architect when ▇▇▇▇▇▇▇▇▇ considers the Work complete. Upon notification, Architect will prepare a list of minor items to be completed or corrected (“Punch List”). Developer and/or its Subcontractors shall proceed promptly to complete and correct items on the Punch List. Failure to include an item on Punch List does not alter the responsibility of Developer to complete all Work in accordance with the Contract Documents.

Appears in 14 contracts

Sources: General Construction Agreement, General Construction Agreement, General Construction Agreement

Punch List. Developer The Contractor shall notify the Architect when ▇▇▇▇▇▇▇▇▇ Contractor considers the Work complete. Upon notification, Architect will prepare a list of minor items to be completed or corrected (“Punch List”). Developer The Contractor and/or its Subcontractors shall proceed promptly to complete and correct items on the Punch List. Failure to include an item on Punch List does not alter the responsibility of Developer the Contractor to complete all Work in accordance with the Contract Documents.

Appears in 9 contracts

Sources: Site Lease, Site Lease, Master Site Lease

Punch List. The Developer shall notify the Architect when ▇▇▇▇▇▇▇▇▇ considers the Work complete. Upon notification, Architect will prepare a list of minor items to be completed or corrected (“Punch List”). The Developer and/or its Subcontractors shall proceed promptly to complete and correct items on the Punch List. Failure to include an item on Punch List does not alter the responsibility of the Developer to complete all Work in accordance with the Contract Documents.

Appears in 7 contracts

Sources: General Construction Agreement, General Construction Agreement, Facilities Lease

Punch List. The Developer shall notify the Architect when ▇▇▇▇▇▇▇▇▇ Developer considers the Work complete. Upon notification, Architect will prepare a list of minor items to be completed or corrected (“Punch List”). The Developer and/or its Subcontractors shall proceed promptly to complete and correct items on the Punch List. Failure to include an item on Punch List does not alter the responsibility of the Developer to complete all Work in accordance with the Contract Documents.

Appears in 4 contracts

Sources: Facilities Lease, Master Facilities Lease, Master Facilities Lease

Punch List. Developer shall notify the Architect and the Construction Manager when ▇▇▇▇▇▇▇▇▇ considers the Work complete. Upon notification, Architect will prepare a list of minor items to be completed or corrected (“Punch List”). Developer and/or its Subcontractors shall proceed promptly to complete and correct items on the Punch List. Failure to include an item on Punch List does not alter the responsibility of Developer to complete all Work in accordance with the Contract Documents.

Appears in 4 contracts

Sources: General Construction Agreement, General Construction Agreement, General Construction Agreement