Quantity of Gas if Measuring Equipment Clause Samples
Quantity of Gas if Measuring Equipment fails
(a) If the Measuring Equipment at a Delivery Point or Receipt Point fails to operate or register accurately for any period of time, then the Quantity of Gas delivered to that Delivery Point or Receipt Point for that period will be the amount estimated by ActewAGL in accordance with clause 16.7(b), unless otherwise agreed between the Parties.
(b) When estimating a Quantity of Gas for the purposes of clause 16.7(a), the amount will be determined by ActewAGL:
(i) by using the registration of any installed check meter which is accurately registering or, if that is not possible, then;
(ii) if the percentage of error can be determined by calibration, tests or mathematical calculation, by varying the Quantity recorded during the period since the Measuring Equipment was previously tested by one half of the error; or
(iii) if neither of the options in clauses 16.7(b)(i) or 16.7(b)(ii) are possible, then by having regard to Gas consumption patterns for that Delivery Point.
Quantity of Gas if Measuring Equipment fails
(a) If the Measuring Equipment at a Delivery Point or Receipt Point fails to operate or register accurately (or to transmit data accurately or correctly) for any period of time, then the Quantity of Gas delivered to that Delivery Point or Receipt Point for that period will be the amount estimated by JGN in accordance with clause 17.3(b), unless otherwise provided for in the Retail Market Procedures or otherwise agreed between the Parties.
(b) When estimating a Quantity of Gas for the purposes of clause 17.4(a), the amount will be determined by JGN:
(i) by using the registration of any installed check meter which is accurately registering or, if that is not possible, then;
(ii) if the percentage of error can be determined by calibration, tests or mathematical calculation, by varying the Quantity recorded during the period since the Measuring Equipment was previously tested by one half of the error; or
(iii) if neither of the options in clauses 17.3(b)(i) or 17.3(b)(ii) are possible, then by having regard to Gas consumption patterns for that Delivery Point.
Quantity of Gas if Measuring Equipment fails
(a) If the Measuring Equipment at a Delivery Point or Receipt Point fails to operate or register accurately (or to transmit data accurately or correctly) for any period of time, then the Quantity of Gas delivered to that Delivery Point or Receipt Point for that period will be the amount estimated by Evoenergy in accordance with clause 17.3(b)15.3(b)15.3(b)16.3(b), unless otherwise provided for in the Retail Market Procedures or otherwise agreed between the Parties.
(b) When estimating a Quantity of Gas for the purposes of clause 15.4(a)15.4(a)16.4(a)17.4(a), the amount will be determined by Evoenergy:
(i) by using the registration of any installed check meter which is accurately registering or, if that is not possible, then:
(ii) if the percentage of error can be determined by calibration, tests or mathematical calculation, by varying the Quantity recorded during the period since the Measuring Equipment was previously tested by one half of the error; or
(iii) if neither of the options in clauses 17.3(b)(i)15.3(b)(i)15.3(b)(i)16.3(b)(i) or 17.3(b)(ii)15.3(b)(ii)15.3(b)(ii)16.3(b)(ii) are possible, then by having regard to Gas consumption patterns for that Delivery Point.
Quantity of Gas if Measuring Equipment fails
(a) If JGN determines, acting reasonably, that the Measuring Equipment at a Delivery Station fails to operate or register accurately (or to transmit data accurately or correctly), then the Quantity of Gas delivered to that Delivery Station for the relevant period will be the amount estimated by JGN in accordance with clause 16.3(b), unless otherwise provided for in the Retail Market Procedures or otherwise agreed between the Parties.
(b) When estimating a Quantity of Gas, the amount will be determined by JGN:
(i) by using the registration of any installed check meter which is accurately registering; or
(ii) if clause 16.3(b)(i) does not apply, by having regard to Gas consumption patterns for that Delivery Point.