Common use of Rail Systems Clause in Contracts

Rail Systems. 1. In-kind repair or replacement of safety components. 2. In-kind repair or replacement of existing track system and passenger loading areas. I. GROUND DISTURBING ACTIVITIES AND SITE WORK, when proposed activities described below substantially conform to the original footprint and/or are performed in previously disturbed soils, including the area where the activity is staged. A. Footings, Foundations, Retaining Walls, Slopes, and Slope Stabilization Systems 1. In-kind repair, replacement, and reinforcement of footings, foundations, retaining walls, slopes, and slope stabilization systems (e.g., gabion baskets, crib walls, soldier pile and lag walls) if related ground disturbing activities are within the boundary of previously disturbed soils. 2. Installation of perimeter drainage (e.g. French drains) when performed in previously disturbed soils.

Appears in 2 contracts

Sources: Programmatic Agreement, Programmatic Agreement