Reactive Power Production Sample Clauses

The Reactive Power Production clause defines the obligations and requirements for generating and managing reactive power within an electrical system. Typically, this clause specifies the minimum and maximum levels of reactive power that a generator must be able to produce or absorb, as well as the conditions under which these requirements apply, such as during normal operation or grid disturbances. By setting these standards, the clause ensures grid stability and voltage control, addressing the need for reliable power quality and system performance.
Reactive Power Production. At continuous rated output, simulations must show that Generator's Facility shall have the capability of dynamically supplying at least 0.33 MVARS at the 230 kV Interconnection Point for each MW supplied when the Facility is tested at 101% of nominal voltage.
Reactive Power Production. At continuous rated output, simulations must show that the Tenaska's Facility shall have the capability of dynamically supplying at least 0.33 MVARS at the 500 kV Interconnection Point for each MW supplied when the Facility is tested at 102% of nominal voltage.
Reactive Power Production. If EirGrid has agreed with the Service Provider that for this Trading Period a level of Reactive Power (Production) shall be made available that is greater than that the contracted level given in this Agreement, then the Contracted Reactive Power (Production)5 shall be set equal to this higher level, but in all other cases the Contracted Reactive Power (Production) shall be set equal to the contracted level given in this Agreement.

Related to Reactive Power Production

  • Reactive Power 1.8.1 The Interconnection Customer shall design its Small Generating Facility to maintain a composite power delivery at continuous rated power output at the Point of Interconnection at a power factor within the range established by the Connecting Transmission Owner on a comparable basis, until NYISO has established different requirements that apply to all similarly situated generators in the New York Control Area on a comparable basis. 1.8.2 The NYISO is required to pay the Interconnection Customer for reactive power, or voltage support service, that the Interconnection Customer provides from the Small Generating Facility in accordance with Rate Schedule 2 of the NYISO Services Tariff.

  • Power Factor Design Criteria (Reactive Power A wind generating plant shall maintain a power factor within the range of 0.95 leading to 0.95 lagging, measured at the Point of Interconnection as defined in this LGIA, if the ISO’s System Reliability Impact Study shows that such a requirement is necessary to ensure safety or reliability. The power factor range standards can be met using, for example without limitation, power electronics designed to supply this level of reactive capability (taking into account any limitations due to voltage level, real power output, etc.) or fixed and switched capacitors if agreed to by the Connecting Transmission Owner for the Transmission District to which the wind generating plant will be interconnected, or a combination of the two. The Developer shall not disable power factor equipment while the wind plant is in operation. Wind plants shall also be able to provide sufficient dynamic voltage support in lieu of the power system stabilizer and automatic voltage regulation at the generator excitation system if the System Reliability Impact Study shows this to be required for system safety or reliability.

  • Reactive Power and Primary Frequency Response 9.6.1 Power Factor Design Criteria

  • Plant The expression ‘Plant’ as used in the tender papers shall mean every temporary accessory necessary or considered necessary by the Engineer to execute, construct, complete and maintain the work and all altered, modified, substituted and additional works ordered in the time and the manner herein provided and all temporary materials and special and other articles and appliance of every sort kind and description whatsoever intended or used therefore.

  • Pipelines Developer shall have no interest in the pipeline gathering system, which gathering system shall remain the sole property of Operator or its Affiliates and shall be maintained at their sole cost and expense.