Rectification of Delay in Implementation. 6.3.1 If the Supplier becomes aware that there is, or there is reasonably likely to be, a Delay under this Call Off Contract: (a) it shall: (i) notify the Customer as soon as practically possible and no later than within two (2) Working Days from becoming aware of the Delay or anticipated Delay; and (ii) include in its notification an explanation of the actual or anticipated impact of the Delay (including the likelihood of such impact where anticipated); and (iii) expeditiously comply with the Customer’s instructions in order to address the impact of the Delay or anticipated Delay; and (iv) use all reasonable endeavours to eliminate or mitigate the consequences of any Delay or anticipated Delay; and (b) if the Delay or anticipated Delay relates to a Milestone in respect which a Delay Payment has been specified in the Implementation Plan, Clause 6.4 (Delay Payments) shall apply.
Appears in 1 contract
Sources: Call Off Terms for Services
Rectification of Delay in Implementation. 6.3.1 If the Supplier becomes aware that there is, or there is reasonably likely to be, a Delay under this Call Off Contract:
(a) it shall:
(i) notify the Customer Contracting Authority as soon as practically possible and no later than within two (2) Working Days from becoming aware of the Delay or anticipated Delay; and;
(ii) include in its notification an explanation of the actual or anticipated impact of the Delay (including the likelihood of such impact where anticipated); andDelay;
(iii) expeditiously comply with the CustomerContracting Authority’s instructions in order to address the impact of the Delay or anticipated Delay; and
(iv) use all reasonable endeavours to eliminate or mitigate the consequences of any Delay or anticipated Delay; and
(b) if the Delay or anticipated Delay relates to a Milestone in respect which a Delay Payment has been specified in the Implementation Plan, Clause 6.4 (Delay Payments) shall apply.
Appears in 1 contract
Sources: Framework Agreement
Rectification of Delay in Implementation. 6.3.1 If the Supplier becomes aware that there is, or there is reasonably likely to be, a Delay under this Call Off Contract:
(a) it shall:
(i) notify the Customer as soon as practically possible and no later than within two (2) Working Days from becoming aware of the Delay or anticipated Delay; and;
(ii) include in its notification an explanation of the actual or anticipated impact of the Delay (including the likelihood of such impact where anticipated); andDelay;
(iii) expeditiously comply with the Customer’s instructions in order to address the impact of the Delay or anticipated Delay; and
(iv) use all reasonable endeavours to eliminate or mitigate the consequences of any Delay or anticipated Delay; and
(b) if the Delay or anticipated Delay relates to a Milestone in respect of which a Delay Payment has been specified in the Implementation Plan, Clause 6.4 (Delay Payments) shall apply.
Appears in 1 contract
Sources: Order Form and Contract Terms
Rectification of Delay in Implementation. 6.3.1 If the Supplier becomes aware that there is, or there is reasonably likely to be, be a Delay under this Call Off Contract:
(a) it shall:
(i) notify the Customer as soon as practically possible and no later than within two (2) Working Days from becoming aware of the Delay or anticipated Delay; and
(ii) include in its notification an explanation of the actual or anticipated impact of the Delay (including the likelihood of such impact where anticipated)Delay; and
(iii) expeditiously comply with the Customer’s instructions in order to address the impact of the Delay or anticipated Delay; and
(iv) use all reasonable endeavours to eliminate or mitigate the consequences of any Delay or anticipated Delay; and
(b) if the Delay or anticipated Delay relates to a Milestone in respect which a Delay Payment has been specified in the Implementation Plan, Clause 6.4 (Delay Payments) shall applyapply Unless the Delay is deemed as resulting from Customer Cause.
Appears in 1 contract