Rectification of Works. In case the survey specified in Clause 8.9 proves that the Works have not been completed according to the Contract, the Engineer's Representative shall instruct the Contractor to rectify the Works. Upon the completion of these rectifying Works, the survey and charting as specified in Clause 8.9 shall again be carried out at no extra cost to the Employer.
Appears in 2 contracts
Sources: Tender Agreement, Tender Agreement
Rectification of Works. In case the survey specified in Clause 8.9 6.9 proves that the Works have not been completed according to the Contract, the Engineer's Representative shall instruct the Contractor to rectify the Works. Upon the completion of these rectifying Works, the survey and charting as specified in Clause 8.9 6.9 shall again be carried out at no extra cost to the Employer.
Appears in 1 contract
Sources: Tender Agreement