Common use of REMOVAL OF IMPROPER WORK AND MATERIALS Clause in Contracts

REMOVAL OF IMPROPER WORK AND MATERIALS. 1) The Engineer shall during the progress of the Works have power to order in writing from time to time: a) the removal from the Site, within such time or times as may be specified in the order, of any materials which, in the opinion of the Engineer, are not in accordance with the Contract. b) the substitution of proper and suitable materials and : c) the removal and proper re-execution, not-withstanding any previous test thereof or interim payment there for, of any-work which in respect of materials or workmanship is not, in the opinion of the Engineer, in accordance with the Contract.

Appears in 2 contracts

Sources: Construction Contract, Construction Contract