Common use of Reporting of Non-Force Majeure Events Clause in Contracts

Reporting of Non-Force Majeure Events. A Party (the “notifying Party”) shall notify the other Parties when the notifying Party becomes aware of its inability to comply with the provisions of this GIA for a reason other than a Force Majeure event. The Parties agree to cooperate with each other and provide necessary information regarding such inability to comply, including the date, duration, reason for the inability to comply, and corrective actions taken or planned to be taken with respect to such inability to comply. Notwithstanding the foregoing, notification, cooperation or information provided under

Appears in 12 contracts

Sources: Generator Interconnection Agreement, Generator Interconnection Agreement, Generator Interconnection Agreement

Reporting of Non-Force Majeure Events. A Each Party (the “notifying Party”) shall notify the other Parties when the notifying Party becomes aware of its inability to comply with the provisions of this GIA LGIA for a reason other than a Force Majeure event. The Parties agree to cooperate with each other and provide necessary information regarding such inability to comply, including the date, duration, reason for the inability to comply, and corrective actions taken or planned to be taken with respect to such inability to comply. Notwithstanding the foregoing, notification, cooperation or information provided underunder this

Appears in 5 contracts

Sources: Large Generator Interconnection Agreement, Large Generator Interconnection Agreement, Large Generator Interconnection Agreement

Reporting of Non-Force Majeure Events. A Each Party (the “notifying Party”) shall notify the other Parties Party(ies) when the notifying Party becomes aware of its inability to comply with the provisions of this GIA LGIA for a reason other than a Force Majeure event. The Parties agree to cooperate with each other and provide necessary information regarding such inability to comply, including the date, duration, reason for the inability to comply, and corrective actions taken or planned to be taken with respect to such inability to comply. Notwithstanding the foregoing, notification, cooperation or information provided under,

Appears in 4 contracts

Sources: Standard Large Generator Interconnection Agreement, Interconnection Agreement, Interconnection Agreement

Reporting of Non-Force Majeure Events. A Each Party (the “notifying Party”) shall notify the other Parties when the notifying Party becomes aware of its inability to comply with the provisions of this GIA LGIA for a reason other than a Force Majeure event. The Parties agree to cooperate with each other and provide necessary information regarding such inability to comply, including the date, duration, reason for the inability to comply, and corrective actions taken or planned to be taken with respect to such inability to comply. Notwithstanding the foregoing, notification, cooperation or information provided under,

Appears in 2 contracts

Sources: Large Generator Interconnection Agreement (Lgia), Large Generator Interconnection Agreement (Lgia)

Reporting of Non-Force Majeure Events. A Each Party (the “notifying Notifying Party”) shall notify the other Parties when the notifying Notifying Party becomes aware of its inability to comply with the provisions of this GIA Agreement for a reason other than a Force Majeure event. The Parties agree to cooperate with each other and provide necessary information regarding such inability to comply, including the date, duration, reason for the inability to comply, and corrective actions taken or planned to be taken with respect to such inability to comply. Notwithstanding the foregoing, notification, cooperation or information provided under63

Appears in 2 contracts

Sources: Interconnection Agreement, Interconnection Agreement

Reporting of Non-Force Majeure Events. A Each Party (the "notifying Party") shall notify the other Parties Party when the notifying Party becomes aware of its inability to comply with the provisions of this GIA Agreement for a reason other than a Force Majeure event. The Parties agree to cooperate with each other and provide necessary information regarding such inability to comply, including the date, duration, reason for the inability to comply, and corrective actions taken or planned to be taken with respect to such inability to comply. Notwithstanding the foregoing, notification, cooperation or information provided underand

Appears in 2 contracts

Sources: Standard Large Generator Interconnection Agreement (Lgia), Standard Large Generator Interconnection Agreement (Lgia)

Reporting of Non-Force Majeure Events. A Each Party (the "notifying Party") shall notify the other Parties when the notifying Party becomes aware of its inability to comply with the provisions of this GIA Agreement for a reason other than a Force Majeure event. The Parties agree to cooperate with each other and provide necessary information regarding such inability to comply, including the date, duration, reason for the inability to comply, and corrective actions taken or planned to be taken with respect to such inability to comply. Notwithstanding the foregoing, notification, cooperation or information provided underthe

Appears in 1 contract

Sources: Large Generator Interconnection Agreement

Reporting of Non-Force Majeure Events. A Each Party (the “notifying Party”) shall notify the other Parties when the notifying Party becomes aware of its inability to comply with the provisions of this GIA LGIA for a reason other than a Force Majeure event. The Parties agree to cooperate with each other and provide necessary information regarding such inability to comply, including the date, duration, reason for the inability to comply, and corrective actions taken or planned to be taken with respect to such inability to comply. Notwithstanding the foregoing, notification, cooperation or information provided underinformation

Appears in 1 contract

Sources: Large Generator Interconnection Agreement

Reporting of Non-Force Majeure Events. A Party (the “notifying Party”) shall notify the other Parties when the notifying Party becomes aware of its inability to comply with the provisions of this GIA for a reason other than a Force Majeure event. The Parties agree to cooperate with each other and provide necessary information regarding such inability to comply, including the date, duration, reason for the inability to comply, and corrective actions taken or planned to be taken with respect to such inability to comply. Notwithstanding the foregoing, notification, cooperation or information provided under.

Appears in 1 contract

Sources: Generator Interconnection Agreement

Reporting of Non-Force Majeure Events. A Each Party (the “notifying Party”) shall notify the other Parties Party when the notifying Party becomes aware of its inability to comply with the provisions of this GIA LGIA for a reason other than a Force Majeure event. The Parties agree to cooperate with each other and provide necessary information regarding such inability to comply, including the date, duration, reason for the inability to comply, and corrective actions taken or planned to be taken with respect to such inability to comply. Notwithstanding the foregoing, notification, cooperation or information provided underthe

Appears in 1 contract

Sources: Standard Large Generator Interconnection Agreement (Lgia)

Reporting of Non-Force Majeure Events. A Each Party (the “notifying Notifying Party”) shall notify the other Parties when the notifying Notifying Party becomes aware of its inability to comply with the provisions of this GIA Agreement for a reason other than a Force Majeure event. The Parties agree to cooperate with each other and provide necessary information regarding such inability to comply, including the date, duration, reason for the inability to comply, and corrective actions taken or planned to be taken with respect to such inability to comply. Notwithstanding the foregoing, notification, cooperation or information provided underinability

Appears in 1 contract

Sources: Interconnection Agreement

Reporting of Non-Force Majeure Events. A Each Party (the "notifying Party") shall notify the other Parties Party when the notifying Party becomes aware of its inability to comply with the provisions of this GIA for a reason other than a Force Majeure event. The Parties agree to cooperate with each other and provide necessary information regarding such inability to comply, including the date, duration, reason for the inability to comply, and corrective actions taken or planned to be taken with respect to such inability to comply. Notwithstanding the foregoing, notification, cooperation or information provided underthe

Appears in 1 contract

Sources: Generator Interconnection Agreement

Reporting of Non-Force Majeure Events. A Each Party (the “notifying Notifying Party”) shall notify the other Parties when the notifying Notifying Party becomes aware of its inability to comply with the provisions of this GIA Agreement for a reason other than a Force Majeure event. The Parties agree to cooperate with each other and provide necessary information regarding such inability to comply, including the date, duration, reason for the inability to comply, and corrective actions taken or planned to be taken with respect to such inability to comply. Notwithstanding the foregoing, notification, cooperation or information provided under,

Appears in 1 contract

Sources: Interconnection Agreement

Reporting of Non-Force Majeure Events. A Party (the “notifying Party”) shall notify the other Parties when the notifying Party becomes aware of its inability to comply with the provisions of this GIA AGREEMENT for a reason other than a Force Majeure event. The Parties agree to cooperate with each other and provide necessary information regarding such inability to comply, including the date, duration, reason for the inability to comply, and corrective actions taken or planned to be taken with respect to such inability to comply. Notwithstanding the foregoing, notification, cooperation or information provided underinformation

Appears in 1 contract

Sources: Interconnection Agreement

Reporting of Non-Force Majeure Events. A Each Party (the “notifying Party”) shall notify the other Parties when the notifying Party becomes aware of its inability to comply with the provisions of this GIA LGIA for a reason other than a Force Majeure event. The Parties agree to cooperate with each other and provide necessary information regarding such inability to comply, including the date, duration, reason for the inability to comply, and corrective actions taken or planned to be taken with respect to such inability to comply. Notwithstanding the foregoing, notification, cooperation or information provided underunder this Article shall

Appears in 1 contract

Sources: Large Generator Interconnection Agreement

Reporting of Non-Force Majeure Events. A Each Party (the "notifying Party") shall notify the other Parties Party when the notifying Party becomes aware of its inability to comply with the provisions of this GIA LGIA for a reason other than a Force Majeure event. The Parties agree to cooperate with each other and provide necessary information regarding such inability to comply, including the date, duration, reason for the inability to comply, and corrective actions taken or planned to be taken with respect to such inability to comply. Notwithstanding the foregoing, notification, cooperation or information provided under,

Appears in 1 contract

Sources: Standard Large Generator Interconnection Agreement (Lgia)