Reporting of Non-Force Majeure Events. Each Party (the "notifying Party") shall notify the other Parties when the notifying Party becomes aware of its inability to comply with the provisions of this Interim GIA for a reason other than a Force Majeure event. The Parties agree to cooperate with each other and provide necessary information regarding such inability to comply, including the date, duration, reason for the inability to comply, and corrective actions taken or planned to be taken with respect to such inability to comply. Notwithstanding the foregoing, notification, cooperation or information provided under this article shall not entitle the Parties receiving such notification to allege a cause for anticipatory breach of this Interim GIA.
Appears in 1 contract
Reporting of Non-Force Majeure Events. Each Party (the "“notifying Party"”) shall notify the other Parties Party when the notifying Party becomes aware of its inability to comply with the provisions of this Interim GIA QF-LGIA for a reason other than a Force Majeure event. The Parties agree to cooperate with each other and provide necessary information regarding such inability to comply, including the date, duration, reason for the inability to comply, and corrective actions taken or planned to be taken with respect to such inability to comply. Notwithstanding the foregoing, notification, cooperation or information provided under this article shall not entitle the Parties Party receiving such notification to allege a cause for anticipatory breach of this Interim GIAQF-LGIA.
Appears in 1 contract
Sources: Qualifying Facility Large Generator Interconnection Agreement (Qf Lgia)
Reporting of Non-Force Majeure Events. Each Party (the "notifying Party") shall notify the other Parties Party when the notifying Party becomes aware of its inability to comply with the provisions of this Interim Transitional Cluster GIA for a reason other than a Force Majeure event. The Parties agree to cooperate with each other and provide necessary information regarding such inability to comply, including the date, duration, reason for the inability to comply, and corrective actions taken or planned to be taken with respect to such inability to comply. Notwithstanding the foregoing, notification, cooperation or information provided under this article shall not entitle the Parties Party receiving such notification to allege a cause for anticipatory breach of this Interim Transitional Cluster GIA.
Appears in 1 contract
Sources: Transitional Cluster Generator Interconnection Agreement
Reporting of Non-Force Majeure Events. Each Party (the "notifying “notifyingNotifying Party"”) shall notify the other Parties PartyParties when the notifying notifyingNotifying Party becomes aware of its inability to comply with the provisions of this Interim GIA LGIA Agreement for a reason other than a Force Majeure event. The Parties agree to cooperate with each other and provide necessary information regarding such inability to comply, including the date, duration, reason for the inability to comply, and corrective actions taken or planned to be taken with respect to such inability to comply. Notwithstanding the foregoing, notification, cooperation or information provided under this article Article shall not entitle the Parties Party receiving such notification to allege a cause for anticipatory breach of this Interim GIALGIA Agreement.
Appears in 1 contract