Request for Information (RFI. An inquiry submitted by the CMR to the DP, requesting clarification or direction. All inquiries other than those considered by the DP to be of low significance, must be submitted and tracked as an RFI. As applicable, each RFI submitted must include information from the CMR regarding any cost or time implications of which he is aware at the time the RFI is submitted. All RFIs must be copied to SCCPSS; in the event SCCPSS wishes to discuss the ASI with the DP or with the CMR, or vice-versa, this should occur immediately upon receipt.