Requests for Draws. For each draw under the Construction Escrow Account, Borrower shall deliver to Lender, a draw request for construction costs in accordance with the Construction Budget, in form reasonably satisfactory to Lender (the “Draw Request”), and stating the amount of disbursement requested, at least ten (10) days before the requested date of disbursement. Each Draw Request shall be approved and signed by Borrower and Lender’s Inspector and shall be accompanied by billing statements, vouchers and invoices as required by Lender or Lender’s Inspector. Lender will release funds from the Construction Escrow Account for the actual costs incurred for construction of the MOB within the estimates set forth in the Construction Budget. Each Draw Request will expressly warrant that the work for which the advance is requested has been performed in all material respects in accordance with the Plans and Specifications and is for actual costs incurred for the construction of the MOB within the estimates set forth in the Construction Budget. Each Draw Request shall constitute an affirmation made by Borrower that Borrower is not in breach of its obligations under this Agreement and that no Default, or any event that with the passage of time would be a Default, has occurred and is continuing. Each Draw Request shall constitute an affirmation that Borrower’s portion of all previously incurred construction costs have been paid in all material respects. Each Draw Request is subject further to the following conditions: 11.3.1. each of the conditions in Section 11.2 shall have been satisfied; 11.3.2. proof, satisfactory to Lender, that all invoices for labor and materials have been paid, except those contained in the current Draw Request; 11.3.3. a list of every material subcontractor who provided labor and/or materials relating to the current Draw Request; 11.3.4. lien waivers from the general contractor and each of the subcontractors contained in the list provided to Lender referenced above in Section 11.3.2; 11.3.5. lien waivers and/or lien releases from payees under previous Draw Requests if not previously submitted; 11.3.6. any written approval required from the USDA for Lender to fund the current Draw Request; 11.3.7. a report signed by Borrower’s Architect, and by Lender’s Inspector, which shall specify the estimated percentage of completion of the MOB, together with detailed comments on the specific work performed since the date of the last report rendered to Lender, and which will certify that all work previously performed in developing, constructing and equipping the MOB has been completed in all material respects in accordance with the Plans and Specifications; 11.3.8. an endorsement to Lender’s mortgagee’s title insurance policy, extending the effective date of the policy to the date of the endorsement, showing no liens of record or additional encumbrances not acceptable to Lender, and increasing the effective amount of the coverage to the total amount outstanding under the Mortgage Note; 11.3.9. a foundation survey shall have been delivered within a reasonable time after completion of the foundation, showing all construction to be within the property lines and disclosing no encroachments or violations of setback or other restrictions; 11.3.10. verification that the actual costs in the aggregate of construction of the MOB do not exceed the aggregate budgeted costs on an itemized basis in any material respect as shown in the Construction Budget, and such other itemization and information with respect to such costs as may be requested by Lender; provided that Borrower may amend the items in the Construction Budget if (a) Borrower gives Lender written notice thereof, (b) the total amount of the Construction Budget is not increased, and (c) the total amount of the Construction Contract is not increased, unless such increases have been previously approved by Lender, Lender’s Inspector, and USDA in writing; 11.3.11. a schedule, reasonably satisfactory to Lender, of the estimated amount and time of disbursements of the cash advances to be made hereunder; 11.3.12. evidence, reasonably satisfactory to Lender, that Borrower has sufficient financial resources to complete the construction and equipping of the MOB to any extent by which the costs shall exceed the amount of the Mortgage Note; 11.3.13. if requested by Lender, proof that all materials and equipment constituting the MOB building or a fixture and any other fixtures incorporated in the MOB have been purchased so that absolute ownership is vested in Borrower; and 11.3.14. All of the above information shall be obtained and submitted to Lender at Borrower’s expense.
Appears in 1 contract
Sources: Mortgage Loan Agreement (Sunlink Health Systems Inc)
Requests for Draws. For each draw under the Construction Escrow Account, Borrower shall deliver to Lender, a draw request for construction costs in accordance with the Construction Budget, in form reasonably satisfactory to Lender (the “Draw Request”), and stating the amount of disbursement requested, at least ten (10) days before the requested date of disbursement. Each Draw Request shall be approved and signed by Borrower and Lender’s Inspector and shall be accompanied by billing statements, vouchers and invoices as required by Lender or Lender’s Inspector. Lender will release funds from the Construction Escrow Account for the actual costs incurred for construction of the MOB within the estimates set forth in the Construction Budget. Each Draw Request will expressly warrant that the work for which the advance is requested has been performed in all material respects in accordance with the Plans and Specifications and is for actual costs incurred for the construction of the MOB within the estimates set forth in the Construction Budget. Each Draw Request shall constitute an affirmation made by Borrower that Borrower is not in breach of its obligations under this Agreement and that no Default, or any event that with the passage of time would be a Default, has occurred and is continuing. Each Draw Request shall constitute an affirmation that Borrower’s portion of all previously incurred construction costs have been paid in all material respects. Each Draw Request is subject further to the following conditions:
11.3.1. each of the conditions in Section 11.2 shall have been satisfied;
11.3.2. proof, satisfactory to Lender, that all invoices for labor and materials have been paid, except those contained in the current Draw Request;
11.3.3. a list of every material subcontractor who provided labor and/or materials relating to the current Draw Request;
11.3.4. lien waivers from the general contractor and each of the subcontractors contained in the list provided to Lender referenced above in Section 11.3.2;
11.3.5. lien waivers and/or lien releases from payees under previous Draw Requests if not previously submitted;
11.3.6. any written approval required from the USDA for Lender to fund the current Draw Request;
11.3.7. a report signed by Borrower’s Architect, and by Lender’s Inspector, which shall specify the estimated percentage of completion of the MOB, together with detailed comments on the specific work performed since the date of the last report rendered to Lender, and which will certify that all work previously performed in developing, constructing and equipping the MOB has been completed in all material respects in accordance with the Plans and Specifications;
11.3.8. an endorsement to Lender’s mortgagee’s title insurance policy, extending the effective date of the policy to the date of the endorsement, showing no liens of record or additional encumbrances not acceptable to Lender, and increasing the effective amount of the coverage to the total amount outstanding under the Mortgage Note;
11.3.9. a foundation survey shall have been delivered within a reasonable time after completion of the foundation, showing all construction to be within the property lines and disclosing no encroachments or violations of setback or other restrictions;
11.3.10. verification that the actual costs in the aggregate of construction of the MOB do not exceed the aggregate budgeted costs on an itemized basis in any material respect as shown in the Construction Budget, and such other itemization and information with respect to such costs as may be requested by Lender; provided that Borrower may amend the items in the Construction Budget if (a) Borrower gives Lender written notice thereof, (b) the total amount of the Construction Budget is not increased, and (c) the total amount of the Construction Contract is not increased, unless such increases have been previously approved by Lender, Lender’s Inspector, and USDA in writing;
11.3.11. a schedule, reasonably satisfactory to Lender, of the estimated amount and time of disbursements of the cash advances to be made hereunder;
11.3.12. evidence, reasonably satisfactory to Lender, that Borrower has sufficient financial resources to complete the construction and equipping of the MOB to any extent by which the costs shall exceed the amount of the Mortgage Note;
11.3.13. if requested by Lender, proof that all materials and equipment constituting the MOB building or a fixture and any other fixtures incorporated in the MOB have been purchased so that absolute ownership is vested in Borrower; and
11.3.14. All of the above information shall be obtained and submitted to Lender at Borrower’s expense.
Appears in 1 contract