The Requirement to Commence Work clause obligates a party, typically a contractor or service provider, to begin performing their contractual duties within a specified timeframe after certain conditions are met, such as contract signing or receipt of a notice to proceed. This clause may detail the exact start date, any prerequisites for commencement, and consequences for failing to start on time. Its core function is to ensure timely initiation of work, providing both parties with clarity and predictability regarding project timelines and helping to prevent unnecessary delays.
Requirement to Commence Work. The Contractor shall under all circumstances commence work under this Contract no later than ten days after the Proceed Order Date of the Proceed Order.
Requirement to Commence Work. Time being of the essence of this Contract, and a material consideration thereof, it is mutually agreed by the parties hereto in case of the Contractor’s failure to complete the construction within the time specified, the Owner will be damaged thereby. The Contractor shall commence performance of its activities on the Site within five days of the date specified in the Proceed Order. The Contractor shall complete construction, except for Minor Items and Permitted Incomplete Work (Scheduled Warranty Items) (see Article 6.1.1), not later than the Material Completion and Occupancy Date, as adjusted by Change Order.
Requirement to Commence Work. The CM/GC shall under all circumstances commence work under this Contract no later than ten days after the Proceed Order Date of a Proceed Order issued subsequent to a Component Change Order or GMP Change Order.
Requirement to Commence Work. The Design-Builder will be required to commence work under this Contract within ten days after the date of the Owner’s written Proceed Order in a Component Change order or GMP Change Order.
Requirement to Commence Work. The CMR shall under all circumstances commence Work under this Contract no later than ten (10) days after the Proceed Order Date of a Component Change Order or GMP Change Order.
Requirement to Commence Work. The Design-Builder shall under all circumstances commence work under this Contract no later than ten days after the Proceed Order Date.
Requirement to Commence Work. The Recipient acknowledges and agrees that it is required to commence work under this Agreement in a timely period following execution of the Agreement. This Section 9 shall survive termination of this Agreement.

Related to Requirement to Commence Work

  • Contract Work Hours and Safety Standards Act The following clauses apply to any Federal-aid construction contract in an amount in excess of $100,000 and subject to the overtime provisions of the Contract Work Hours and Safety Standards Act. These clauses shall be inserted in addition to the clauses required by 29 CFR 5.5(a) or 29 CFR 4.6. As used in this paragraph, the terms laborers and mechanics include watchmen and guards.