Common use of Requirements after Termination Clause in Contracts

Requirements after Termination. 21.4.1 Upon Termination of this Contract Agreement in accordance with the terms of this Article 21, the Contractor shall comply with and conform to the following: 21.4.2 Deliver to the Authority all Project Assets which shall have become the property of the Authority under this Article21; 21.4.3 Deliver all relevant records, reports, intellectual property and other licences pertaining to the Works, other design documents and in case of Termination occurring after the Project Commissioning Certificate has been issued, the ‘as built’ drawings for the Works; 21.4.4 Transfer and/or deliver all Applicable Permits to the extent permissible under Applicable Laws; and 21.4.5 Vacate the Project Site within 15days.

Appears in 2 contracts

Sources: Draft Contract Agreement, Contract Agreement