Requirements for Substantial Completion. The Work (or a designated portion thereof) shall be deemed Substantially Completed on the date when all of the following events or conditions shall have occurred: 11.5.1 Owner may use and occupy the Project or, if requested by Owner, portions thereof without interference for all of its intended purposes under this Agreement; 11.5.2 only Punchlist items, if any, remain incomplete, provided said Punchlist items, in Owner’s judgment, do not interfere with Owner’s use and occupancy; 11.5.3 Architect shall have issued a Certificate of Substantial Completion; and 11.5.4 Issuance of a Temporary Certificate of Occupancy.