Common use of Requirements for the programme Clause in Contracts

Requirements for the programme. State whether a programme is required and, if it is, what form it is to be in, what information is to be shown on it, when it is to be submitted and when it is to be updated No programme is required.

Appears in 1 contract

Sources: Call Off Agreement

Requirements for the programme. State whether a programme is required and, if it is, state what form it is to be in, what information is to be shown on it, when it is to be submitted and when it is to be updated No programme updated. State what the use of the works is requiredintended to be at their Completion as defined in Clause 11.2(1).

Appears in 1 contract

Sources: Nec3 Engineering and Construction Contract