Requirements for the programme. The Contractor submits a programme within 3 days of contract award. The programme is submitted in 3 copies; one electronic editable format (ms. Word or primavera), one electronic pdf format and one hard copy. The programme indicates the start and end dates and duration for every activity and milestone The contractor revises the programme in intervals not exceeding two weeks. The contractor further revises the programme within two days of deviation from the last approved programme.
Appears in 2 contracts
Sources: Nec3 Engineering and Construction Short Contract (Ecsc3), Nec3 Engineering and Construction Short Contract (Ecsc3)