Rescheduling of Tests. If the Independent Engineer certifies to the TNRDC and Authority and the Concessionaire that it is unable to issue the Completion Certificate or Provisional Certificate, as the case may be, because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Concessionaire shall be entitled to re-schedule the Tests and hold the same as soon as reasonably practicable.
Appears in 2 contracts
Sources: Concession Agreement, Concession Agreement
Rescheduling of Tests. If the Independent Engineer or the Independent Panel certifies to the TNRDC and Authority and the Concessionaire that it is unable to issue the Completion Certificate or Provisional Certificate, as the case may be, because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Concessionaire shall be entitled to re-schedule the Tests and hold the same as soon as reasonably practicable.
Appears in 2 contracts
Sources: Concession Agreement, Concession Agreement
Rescheduling of Tests. If the Independent Engineer certifies to the TNRDC and Authority / SSNNL / FED and the Concessionaire that it is unable to issue the Completion Certificate or Provisional Certificate, as the case may be, because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Concessionaire shall be entitled to re-schedule the Tests and hold the same as soon as reasonably practicable.
Appears in 1 contract
Sources: Concession Agreement
Rescheduling of Tests. If the Independent Engineer certifies to the TNRDC and Authority and the Concessionaire that it is unable to issue the Completion Certificate or Provisional Certificate, as the case may be, because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Concessionaire shall be entitled to re-re- schedule the Tests and hold the same as soon as reasonably practicable.
Appears in 1 contract
Sources: Concession Agreement
Rescheduling of Tests. ▇▇▇.▇▇▇▇▇▇.▇▇▇ Downloaded If the Independent Engineer certifies to the TNRDC and Authority and the Concessionaire that it is unable to issue the Completion Certificate or Provisional Certificate, as the case may be, because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Concessionaire shall be entitled to re-schedule the Tests and hold the same as soon as reasonably practicable.
Appears in 1 contract
Sources: Concession Agreement
Rescheduling of Tests. If the Independent Engineer certifies to the TNRDC and Concessioning Authority and the Concessionaire that it is unable to issue the Completion Certificate or Provisional Certificate, as the case may be, because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Concessionaire shall be entitled to re-schedule the Tests and hold the same as soon as reasonably practicable.
Appears in 1 contract
Sources: Concession Agreement
Rescheduling of Tests. If the Independent Engineer certifies to the TNRDC and Authority and the Concessionaire that it is unable to issue the Completion Certificate or Provisional Certificate, as the case may be, because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Concessionaire shall be entitled to re-schedule the Tests and hold the same as soon as reasonably practicable.
Appears in 1 contract
Sources: Concession Agreement
Rescheduling of Tests. ▇▇▇.▇▇▇▇▇▇.▇▇▇ If the Independent Engineer certifies to the TNRDC and Authority and the Concessionaire that it is unable to issue the Completion Certificate or Provisional Certificate, as the case may be, because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Concessionaire shall be entitled to re-schedule the Tests and hold the same as soon as reasonably practicable.
Appears in 1 contract
Sources: Concession Agreement
Rescheduling of Tests. If the Independent Engineer certifies to the TNRDC and Authority and the Concessionaire that it is unable to issue the Completion Certificate or Provisional Certificate, as the case may be, because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Concessionaire shall be entitled to re-schedule reschedule the Tests and hold the same as soon as reasonably practicable.
Appears in 1 contract
Sources: Concession Agreement
Rescheduling of Tests. 14.6.1 If the Independent Engineer certifies to the TNRDC and Authority and the Concessionaire that it is unable to issue the Completion Certificate or Provisional Certificate, as the case may be, because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Concessionaire shall be entitled to re-schedule the Tests and hold the same as soon as reasonably practicable.
Appears in 1 contract
Sources: Concession Agreement
Rescheduling of Tests. If the Independent Engineer Supervision Committee certifies to the TNRDC and Authority and the Concessionaire that it is unable to issue the Completion Certificate Certificate-1 or Completion Certificate-2 or Provisional CertificateCertificate for the Project, as the case may be, because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Concessionaire shall be entitled to re-re- schedule the Tests and hold the same as soon as reasonably practicable.
Appears in 1 contract
Sources: Concession Agreement