Common use of Resource Loading Clause in Contracts

Resource Loading. 3.9.1.2.12.1. CMR will assign manpower-loading for each construction activity in the Master Project Schedule. Activities’ resource loading must be based on the CMR’s estimate used in pricing the Work. 3.9.1.2.12.2. Resources and labor (man-hours) allocated to each activity must be consistent with activity duration as well as scope and supported by the CMR’s estimate and industry standard estimating / productivity guides such as “Means” and/or “▇▇▇▇▇▇’▇”. 3.9.1.2.12.3. The schedule activities must not be resource leveled or resource constrained.