Common use of Revised Baseline Schedule Clause in Contracts

Revised Baseline Schedule. Design-Builder shall submit and Department shall approve a Revised Baseline Schedule (i) as a condition precedent to Department’s issuance of NTP and (ii) whenever required in accordance with Section 2.3 of the Technical Requirements. Department reserves the right to withhold approval for all or part of Design-Builder’s Applications for Early Work Payment or Applications for Payment, as applicable, until such time Design-Builder furnishes an approved Revised Baseline Schedule.

Appears in 3 contracts

Sources: Comprehensive Agreement, Comprehensive Agreement, Comprehensive Agreement