Revisions to Schedule. If the Project Commencement Date, Contractor Commencement Date or a Scheduled Commencement Date is changed or altered by the Construction Manager or Owner, the Contractor shall commence Work within (3) three days notification; however, the Work durations per the Project Schedule or other schedules provided and agreed to, shall remain the same. Such durations shall not change unless agreed to by the Construction Manager or Owner and Contractor in writing. Contractor’s manpower shall be scheduled accordingly.
Appears in 2 contracts
Sources: Construction Agreement, Construction Agreement