Common use of Revisions to Scheduled Maintenance Plan Clause in Contracts

Revisions to Scheduled Maintenance Plan. (a) No later than 30 days prior to the commencement of any Quarter, Project Co may submit to the NHS Representative a revision to the applicable Scheduled Maintenance Plan for the Contract Year in which the relevant Quarter falls showing the effect of the proposed changes. If Project Co is entitled to proceed with such changes pursuant to Schedule 10 - Review Procedure, then the Scheduled Maintenance Plan as so amended shall become the Scheduled Maintenance Plan in respect of that Quarter. (b) Without limiting the comments that may be made pursuant to Schedule 10 - Review Procedure in relation to the submission of any Scheduled Maintenance Plan, NHS, acting reasonably, may comment "Reviewed as Noted" or "Rejected" on any revision to any Scheduled Maintenance Plan pursuant to this Section 27.2 on the grounds that: (i) performing the Scheduled Maintenance in the period or at the times suggested would (on the balance of probabilities) materially interfere with the performance of the Hospital Services and such material interference could be avoided or mitigated by Project Co rescheduling the Scheduled Maintenance; (ii) performing the Scheduled Maintenance in the period or at the times suggested would (on the balance of probabilities) materially adversely affect the safety of patients, volunteers or other users of the Facility and such material adverse effect could be avoided or mitigated by Project Co rescheduling the Scheduled Maintenance; or (iii) the period for performing the Scheduled Maintenance would (on the balance of probabilities) exceed the period reasonably required for the relevant work.

Appears in 1 contract

Sources: Project Agreement

Revisions to Scheduled Maintenance Plan. (a) No later than 30 days prior to the commencement of any Quartercalendar quarter, Project Co may submit to the NHS HHS Representative a revision to the applicable Scheduled Maintenance Plan for the Contract Year in which the relevant Quarter calendar quarter year falls showing the effect of the proposed changes. If Project Co is entitled to proceed with such changes pursuant to Schedule 10 - Review Procedure, then the Scheduled Maintenance Plan as so amended shall become the Scheduled Maintenance Plan in respect of that Quartercalendar quarter year. (b) Without limiting the comments that may be made pursuant to Schedule 10 - Review Procedure in relation to the submission of any Scheduled Maintenance Plan, NHSHHS, acting reasonably, may comment "Reviewed as Noted" or "Rejected" on any revision to any Scheduled Maintenance Plan pursuant to this Section 27.2 26.2 on the grounds that: (i) performing the Scheduled Maintenance in the period or at the times suggested would (on the balance of probabilities) materially interfere with the performance of the Hospital Services and such material interference could be avoided or mitigated by Project Co rescheduling the Scheduled Maintenance; (ii) performing the Scheduled Maintenance in the period or at the times suggested would (on the balance of probabilities) materially adversely affect the safety of patients, volunteers or other users of the Facility and such material adverse effect could be avoided or mitigated by Project Co rescheduling the Scheduled Maintenance; or (iii) the period for performing the Scheduled Maintenance would (on the balance of probabilities) exceed the period reasonably required for the relevant work.

Appears in 1 contract

Sources: Project Agreement

Revisions to Scheduled Maintenance Plan. (a) No later than 30 days prior to the commencement of any Quartercalendar quarter, Project Co may submit to the NHS HRRH Representative a revision to the applicable Scheduled Maintenance Plan for the Contract Year in which the relevant Quarter calendar quarter year falls showing the effect of the proposed changes. If Project Co is entitled to proceed with such changes pursuant to Schedule 10 - Review Procedure, then the Scheduled Maintenance Plan as so amended shall become the Scheduled Maintenance Plan in respect of that Quartercalendar quarter year. (b) Without limiting the comments that may be made pursuant to Schedule 10 - Review Procedure in relation to the submission of any Scheduled Maintenance Plan, NHSHRRH, acting reasonably, may comment "Reviewed as Noted" or "Rejected" on any revision to any Scheduled Maintenance Plan pursuant to this Section 27.2 26.2 on the grounds that: (i) performing the Scheduled Maintenance in the period or at the times suggested would (on the balance of probabilities) materially interfere with the performance of the Hospital Services and such material interference could be avoided or mitigated by Project Co rescheduling the Scheduled Maintenance; (ii) performing the Scheduled Maintenance in the period or at the times suggested would (on the balance of probabilities) materially adversely affect the safety of patients, volunteers or other users of the Facility and such material adverse effect could be avoided or mitigated by Project Co rescheduling the Scheduled Maintenance; or (iii) the period for performing the Scheduled Maintenance would (on the balance of probabilities) exceed the period reasonably required for the relevant work.

Appears in 1 contract

Sources: Project Agreement