Revisions. (a) Project Co will ensure that Submittals keep the same, unique reference number throughout the review process, and that all subsequent revisions of the same Submittal are identified by a sequential revision number. Correspondence related to such Submittal will reference the reference number and revision number. (b) Re-submittals will clearly show all revisions from the previous Submittal. Bound documents, including reports and manuals, will contain a preface that clearly states how revisions are marked and the previous revision number against which the revisions have been marked. A consistent format for mark-ups of documents will be used (e.g. deletions struck out and additions underscored). Revised portions of drawings will be clearly marked (with appropriate means to visually distinguish between the parts of the drawing that are revised and the parts that are not revised) and the revision number and description of the revision will be included on the drawing. (c) All revisions on print media will be initialled by hand by the individual designer, design checker and, where applicable, by the drafter and the drafting checker and will identify the individuals who initialled the Submittal. Electronic versions of the Submittal will identify the individuals who initialled the revisions to the printed version of the Submittal. (d) Project Co will keep all Reviewed Drawings and Specifications current. If any Reviewed Drawings and Specifications are revised as part of a Submittal, all other Reviewed Drawings and Specifications relying on or based on that Reviewed Drawings and Specifications will also be revised accordingly. All such revised Reviewed Drawings and Specifications will also be submitted with the Submittal to which it relates.
Appears in 2 contracts
Sources: Review Procedure Agreement, User Consultation and Design Review Agreement
Revisions. (a) Project Co will ensure that Submittals keep the same, unique reference number throughout the review process, and that all subsequent revisions of the same Submittal are identified by a sequential revision number. Correspondence related to such Submittal will reference the reference number and revision number.
(b) Re-submittals will clearly show all revisions from the previous Submittal. Bound documents, including reports and manuals, will contain a preface that clearly states how revisions are marked and the previous revision number against which the revisions have been marked. A consistent format for mark-ups of documents will be used (e.g. deletions struck out and additions underscored). Revised portions of drawings will be clearly marked (with appropriate means to visually distinguish between the parts of the drawing that are revised and the parts that are not revised) and the revision number and description of the revision will be included on the drawing.
(c) All revisions on print media will be initialled by hand by the individual designer, design checker and, where applicable, by the drafter and the drafting checker and will identify the individuals persons who initialled the Submittal. Electronic versions of the Submittal will identify the individuals persons who initialled the revisions to the printed version of the Submittal.
(d) Project Co will keep all Reviewed Drawings and Specifications current. If any Reviewed Drawings and Specifications are revised as part of a Submittal, all other Reviewed Drawings and Specifications relying on or based on that Reviewed Drawings and Specifications will also be revised accordingly. All such revised Reviewed Drawings and Specifications will also be submitted with the Submittal to which it relates.
Appears in 2 contracts
Sources: Review Procedure Agreement, Review Procedure
Revisions.
(a) Project Co will ensure that Submittals keep the same, unique reference number throughout the review process, and that all subsequent revisions of the same Submittal are identified by a sequential revision number. Correspondence related to such Submittal will reference the reference number and revision number.
(b) Re-submittals will clearly show all revisions from the previous Submittal. Bound documents, including reports and manuals, will contain a preface that clearly states how revisions are marked and the previous revision number against which the revisions have been marked. A consistent format for mark-ups of documents will be used (e.g. deletions struck out and additions underscored). Revised portions of drawings will be clearly marked (with appropriate means to visually distinguish between the parts of the drawing that are revised and the parts that are not revised) and the revision number and description of the revision will be included on the drawing.
(c) All revisions on print media will be initialled by hand by the individual designer, design checker and, where applicable, by the drafter and the drafting checker and will identify the individuals persons who initialled the Submittal. Electronic versions of the Submittal will identify the individuals persons who initialled the revisions to the printed version of the Submittal.
(d) Project Co will keep all Reviewed Drawings and Specifications current. If any Reviewed Drawings and Specifications are revised as part of a Submittal, all other Reviewed Drawings and Specifications relying on or based on that Reviewed Drawings and Specifications will also be revised accordingly. All such revised Reviewed Drawings and Specifications will also be submitted with the Submittal to which it relates.
ATTACHMENT 1 ( APPENDIX 2B) SUBMITTAL SCHEDULE
Appears in 2 contracts
Sources: User Consultation and Design Review Agreement, User Consultation and Design Review Agreement
Revisions. (a) Project Co
7.1 The Design-Builder will ensure that Submittals keep the same, unique reference number throughout the review process, and that all subsequent revisions of the same Submittal are identified by a sequential revision number. Correspondence related to such Submittal will reference the reference number and revision number.
(b) 7.2 Re-submittals will clearly show all revisions from the previous Submittal. Bound documents, including reports and manuals, will contain a preface that clearly states how revisions are marked and the previous revision number against which the revisions have been marked. A consistent format for mark-ups of documents will be used (e.g. deletions struck out and additions underscored). Revised portions of drawings will be clearly marked (with appropriate means to visually distinguish between the parts of the drawing that are revised and the parts that are not revised) and the revision number and description of the revision will be included on the drawing.
(c) 7.3 All revisions on print media will be initialled by hand by the individual designer, design checker and, where applicable, by the drafter and the drafting checker and will identify the individuals persons who initialled the Submittal. Electronic versions of the Submittal will identify the individuals persons who initialled the revisions to the printed version of the Submittal.
(d) Project Co 7.4 The Design-Builder will keep all Reviewed Drawings and Specifications current. If any Reviewed Drawings and Specifications are revised as part of a Submittal, all other Reviewed Drawings and Specifications relying on or based on that Reviewed those Drawings and Specifications will also be revised accordingly. All such revised Reviewed Drawings and Specifications will also be submitted with the Submittal to which it relates.
Appears in 1 contract
Sources: Design Build Agreement
Revisions. (a) Project Co will ensure that Submittals keep the same, unique reference number throughout the review process, and that all subsequent revisions of the same Submittal are identified by a sequential revision number. Correspondence related to such Submittal will reference the reference number and revision number.
(b) Re-submittals will clearly show all revisions from the previous Submittal. Bound documents, including reports and manuals, will contain a preface that clearly states how revisions are marked and the previous revision number against which the revisions have been marked. A consistent format for mark-ups of documents will be used (e.g. deletions struck out and additions underscored). Revised portions of drawings will be clearly marked (with appropriate means to visually distinguish between the parts of the drawing that are revised and the parts that are not revised) and the revision number and description of the revision will be included on the drawing.
(c) All revisions on print media will be initialled by hand by the individual designer, design checker and, where applicable, by the drafter and the drafting checker and will identify the individuals persons who initialled the Submittal. Electronic versions of the Submittal will identify the individuals persons who initialled the revisions to the printed version of the Submittal.
(d) Project Co will keep all Reviewed Drawings and Specifications current. If any Reviewed Drawings and Specifications are revised as part of a Submittal, all other Reviewed Drawings and Specifications relying on or based on that Reviewed Drawings and Specifications will also be revised accordingly. All such revised Reviewed Drawings and Specifications will also be submitted with the Submittal to which it relates.
ATTACHMENT 1 SUBMITTAL SCHEDULE
Appears in 1 contract
Sources: Review Procedure Agreement
Revisions. (a) Project Co 7.1 The Design-Builder will ensure that Submittals keep the same, unique reference number throughout the review process, and that all subsequent revisions of the same Submittal are identified by a sequential revision numbernumber and identified and tracked in the Submittal log. Correspondence related to such Submittal will reference the reference number and revision number.
(b) 7.2 Re-submittals will clearly show all revisions from the previous Submittal. Bound documents, including reports and manuals, will contain a preface that clearly states how revisions are marked and the previous revision number against which the revisions have been markedmarked and highlighted within the document. A consistent format for mark-ups ▇▇▇▇-ups of documents will be used (e.g. deletions struck out and additions underscored). Revised portions of drawings will be clearly marked (with appropriate means to visually distinguish between the parts of the drawing that are revised and the parts that are not revised) and the revision number and description of the revision will be included on the drawing.
(c) 7.3 All revisions on print media will be initialled by hand by the individual designer, design checker and, where applicable, by the drafter and the drafting checker and will identify the individuals persons who initialled the Submittal. Electronic versions of the Submittal will identify the individuals persons who initialled the revisions to the printed version of the Submittal.
(d) Project Co 7.4 The Design-Builder will keep all Reviewed Drawings and Specifications current. If any Reviewed Drawings and Specifications are revised as part of a Submittal, all other Reviewed Drawings and Specifications relying on or based on that Reviewed those Drawings and Specifications will also be revised accordingly. All such revised Reviewed Drawings and Specifications will also be submitted with the Submittal to which it relates.
Appears in 1 contract
Sources: Design Build Agreement
Revisions. (a) Project Co 9.1 The Design-Builder will ensure that Submittals keep the same, unique reference number throughout the review process, and that all subsequent revisions of the same Submittal are identified by a sequential revision numbernumber and identified and tracked in the Submittal log. Correspondence related to such Submittal will reference the reference number and revision number.
(b) 9.2 Re-submittals will clearly show all revisions from the previous Submittal. Bound documents, including reports and manuals, will contain a preface that clearly states how revisions are marked and the previous revision number against which the revisions have been markedmarked and highlighted within the document. A consistent format for mark-ups of documents will be used (e.g. deletions struck out and additions underscored). Revised portions of drawings will be clearly marked (with appropriate means to visually distinguish between the parts of the drawing that are revised and the parts that are not revised) and the revision number and description of the revision will be included on the drawing.
(c) 9.3 All revisions on print media will be initialled by hand by the individual designer, design checker and, where applicable, by the drafter and the drafting checker and will identify the individuals who initialled the Submittal. Electronic versions of the Submittal will identify the individuals who initialled the revisions to the printed version of the Submittal.
(d) Project Co 9.4 The Design-Builder will keep all Reviewed Drawings and Specifications current. If any Reviewed Drawings and Specifications are revised as part of a Submittal, all other Reviewed Drawings and Specifications relying on or based on that Reviewed those Drawings and Specifications will also be revised accordingly. All such revised Reviewed Drawings and Specifications will also be submitted with the Submittal to which it relates.
Appears in 1 contract
Sources: Design Build Agreement
Revisions. (a) Project Co will ensure that Submittals keep the same, unique reference number throughout the review process, and that all subsequent revisions of the same Submittal are identified by a sequential revision number. Correspondence related to such Submittal will reference the reference number and revision number.
(b) Re-submittals will clearly show all revisions from the previous Submittal. Bound documents, including reports and manuals, will contain a preface that clearly states how revisions are marked and the previous revision number against which the revisions have been marked. A consistent format for mark-ups of documents will be used (e.g. deletions struck out and additions underscored). Revised portions of drawings will be clearly marked (with appropriate means to visually distinguish between the parts of the drawing that are revised and the parts that are not revised) and the revision number and description of the revision will be included on the drawing.
(c) All revisions on print media will be initialled by hand by the individual designer, design checker and, where applicable, by the drafter and the drafting checker and will identify the individuals who initialled the Submittal. Electronic versions of the Submittal will identify the individuals who initialled the revisions to the printed version of the Submittal.
(d) Project Co will keep all Reviewed Drawings and Specifications current. If any Reviewed Drawings and Specifications are revised as part of a Submittal, all other Reviewed Drawings and Specifications relying on or based on that those Reviewed Drawings and Specifications will also be revised accordingly. All such revised Reviewed Drawings and Specifications will also be submitted with the Submittal to which it relates.
Appears in 1 contract
Sources: Review Procedure Agreement
Revisions. (a) Project Co 10.1 The Design-Builder will ensure that Submittals keep the same, unique reference number throughout the review process, and that all subsequent revisions of the same Submittal are identified by a sequential revision number. Correspondence related to such Submittal will reference the reference number and revision number.
(b) 10.2 Re-submittals will clearly show all revisions from the previous Submittal. Bound documents, including reports and manuals, will contain a preface that clearly states how revisions are marked and the previous revision number against which the revisions have been marked. A consistent format for mark-ups ▇▇▇▇-ups of documents will be used (e.g. deletions struck out and additions underscored). Revised portions of drawings will be clearly marked (with appropriate means to visually distinguish between the parts of the drawing that are revised and the parts that are not revised) and the revision number and description of the revision will be included on the drawing.
(c) 10.3 All revisions on print media will be initialled by hand by the individual designer, design checker and, where applicable, by the drafter and the drafting checker and will identify the individuals persons who initialled the Submittal. Electronic versions of the Submittal will identify the individuals persons who initialled the revisions to the printed version of the Submittal.
(d) Project Co 10.4 The Design-Builder will keep all Reviewed Drawings and Specifications current. If any Reviewed Drawings and Specifications are revised as part of a Submittal, all other Reviewed Drawings and Specifications relying on or based on that Reviewed Drawings and Specifications will also be revised accordingly. All such revised Reviewed Drawings and Specifications will also be submitted with the Submittal to which it relates.
Appears in 1 contract
Sources: Design Build Agreement
Revisions. (a) Project Co 8.1 The Design-Builder will ensure that Submittals keep the same, unique reference number throughout the review process, and that all subsequent revisions of the same Submittal are identified by a sequential revision numbernumber and identified and tracked in the Submittal log. Correspondence related to such Submittal will reference the reference number and revision number.
(b) 8.2 Re-submittals will clearly show all revisions from the previous Submittal. Bound documents, including reports and manuals, will contain a preface that clearly states how revisions are marked and the previous revision number against which the revisions have been markedmarked and highlighted within the document. A consistent format for mark-ups of documents will be used (e.g. deletions struck out and additions underscored). Revised portions of drawings will be clearly marked (with appropriate means to visually distinguish between the parts of the drawing that are revised and the parts that are not revised) and the revision number and description of the revision will be included on the drawing.
(c) 8.3 All revisions on print media will be initialled by hand by the individual designer, design checker and, where applicable, by the drafter and the drafting checker and will identify the individuals persons who initialled the Submittal. Electronic versions of the Submittal will identify the individuals persons who initialled the revisions to the printed version of the Submittal.
(d) Project Co 8.4 The Design-Builder will keep all Reviewed Drawings and Specifications current. If any Reviewed Drawings and Specifications are revised as part of a Submittal, all other Reviewed Drawings and Specifications relying on or based on that Reviewed those Drawings and Specifications will also be revised accordingly. All such revised Reviewed Drawings and Specifications will also be submitted with the Submittal to which it relates.
Appears in 1 contract
Sources: Design Build Agreement
Revisions. (a) Project Co 7.1 The Design-Builder will ensure that Submittals keep the same, unique reference number throughout the review process, and that all subsequent revisions of the same Submittal are identified by a sequential revision number. Correspondence related to such Submittal will reference the reference number and revision number.
(b) 7.2 Re-submittals will clearly show all revisions from the previous Submittal. Bound documents, including reports and manuals, will contain a preface that clearly states how revisions are marked and the previous revision number against which the revisions have been marked. A consistent format for mark-ups ▇▇▇▇-ups of documents will be used (e.g. deletions struck out and additions underscored). Revised portions of drawings will be clearly marked (with appropriate means to visually distinguish between the parts of the drawing that are revised and the parts that are not revised) and the revision number and description of the revision will be included on the drawing.
(c) 7.3 All revisions on print media will be initialled by hand by the individual designer, design checker and, where applicable, by the drafter and the drafting checker and will identify the individuals persons who initialled the Submittal. Electronic versions of the Submittal will identify the individuals persons who initialled the revisions to the printed version of the Submittal.
(d) Project Co 7.4 The Design-Builder will keep all Reviewed Drawings and Specifications current. If any Reviewed Drawings and Specifications are revised as part of a Submittal, all other Reviewed Drawings and Specifications relying on or based on that Reviewed those Drawings and Specifications will also be revised accordingly. All such revised Reviewed Drawings and Specifications will also be submitted with the Submittal to which it relates.
Appears in 1 contract
Sources: Design Build Agreement
Revisions.
(a) Project Co will ensure that Submittals keep the same, unique reference number throughout the review process, and that all subsequent revisions of the same Submittal are identified by a sequential revision number. Correspondence related to such Submittal will reference the reference number and revision number.
(b) Re-submittals will clearly show all revisions from the previous Submittal. Bound documents, including reports and manuals, will contain a preface that clearly states how revisions are marked and the previous revision number against which the revisions have been marked. A consistent format for mark-ups of documents will be used (e.g. deletions struck out and additions underscored). Revised portions of drawings will be clearly marked (with appropriate means to visually distinguish between the parts of the drawing that are revised and the parts that are not revised) and the revision number and description of the revision will be included on the drawing.
(c) All revisions on print media will be initialled by hand by the individual designer, design checker and, where applicable, by the drafter and the drafting checker and will identify the individuals who initialled the Submittal. Electronic versions of the Submittal will identify the individuals who initialled the revisions to the printed version of the Submittal.
(d) Project Co will keep all Reviewed Drawings and Specifications current. If any Reviewed Drawings and Specifications are revised as part of a Submittal, all other Reviewed Drawings and Specifications relying on or based on that Reviewed Drawings and Specifications will also be revised accordingly. All such revised Reviewed Drawings and Specifications will also be submitted with the Submittal to which it relates.
Appears in 1 contract
Sources: Review Procedure
Revisions. (a) Project Co 8.1 The Design-Builder will ensure that Submittals keep the same, unique reference number throughout the review process, and that all subsequent revisions of the same Submittal are identified by a sequential revision numbernumber and identified and tracked in the Submittal log. Correspondence related to such Submittal will reference the reference number and revision number.
(b) 8.2 Re-submittals will clearly show all revisions from the previous Submittal. Bound documents, including reports and manuals, will contain a preface that clearly states how revisions are marked and the previous revision number against which the revisions have been markedmarked and highlighted within the document. A consistent format for mark-ups of documents will be used (e.g. deletions struck out and additions underscored). Revised portions of drawings will be clearly marked (with appropriate means to visually distinguish between the parts of the drawing that are revised and the parts that are not revised) and the revision number and description of the revision will be included on the drawing.
(c) 8.3 All revisions on print media will be initialled initialed by hand by the individual designer, design checker and, where applicable, by the drafter and the drafting checker and will identify the individuals persons who initialled initialed the Submittal. Electronic versions of the Submittal will identify the individuals persons who initialled initialed the revisions to the printed version of the Submittal.
(d) Project Co 8.4 The Design-Builder will keep all Reviewed Drawings and Specifications current. If any Reviewed Drawings and Specifications are revised as part of a Submittal, all other Reviewed Drawings and Specifications relying on or based on that Reviewed those Drawings and Specifications will also be revised accordingly. All such revised Reviewed Drawings and Specifications will also be submitted with the Submittal to which it relates.
Appears in 1 contract
Sources: Design Build Agreement
Revisions. (a) Project Co 8.1 The Design-Builder will ensure that Submittals keep the same, unique reference number throughout the review process, and that all subsequent revisions of the same Submittal are identified by a sequential revision numbernumber and identified and tracked in the Submittal log. Correspondence related to such Submittal will reference the reference number and revision number.
(b) 8.2 Re-submittals will clearly show all revisions from the previous Submittal. Bound documents, including reports and manuals, will contain a preface that clearly states how revisions are marked and the previous revision number against which the revisions have been markedmarked and highlighted within the document. A consistent format for mark-ups ▇▇▇▇-ups of documents will be used (e.g. deletions struck out and additions underscored). Revised portions of drawings will be clearly marked (with appropriate means to visually distinguish between the parts of the drawing that are revised and the parts that are not revised) and the revision number and description of the revision will be included on the drawing.
(c) 8.3 All revisions on print media will be initialled by hand by the individual designer, design checker and, where applicable, by the drafter and the drafting checker and will identify the individuals persons who initialled the Submittal. Electronic versions of the Submittal will identify the individuals persons who initialled the revisions to the printed version of the Submittal.
(d) Project Co 8.4 The Design-Builder will keep all Reviewed Drawings and Specifications current. If any Reviewed Drawings and Specifications are revised as part of a Submittal, all other Reviewed Drawings and Specifications relying on or based on that Reviewed those Drawings and Specifications will also be revised accordingly. All such revised Reviewed Drawings and Specifications will also be submitted with the Submittal to which it relates.
Appears in 1 contract
Sources: Design Build Agreement
Revisions. (a) Project Co will ensure that that:
(a) all Operating Period Submittals keep the same, unique reference number throughout the review process, and that all subsequent revisions of the same Operating Period Submittal are identified by the same unique reference number, modified by a sequential revision number. Correspondence related to such Operating Period Submittal will reference the reference number and revision number.;
(b) Reany re-submittals will submittal of an Operating Period Submittal clearly show shows all revisions from the previous Operating Period Submittal. Bound documents, including reports and manuals, will contain a preface that clearly states how revisions are marked and the previous revision number against which the revisions have been marked. A consistent format for mark-ups of documents will be used (e.g. deletions struck out and additions underscored). Revised portions of drawings will be clearly marked (with appropriate means to visually distinguish between the parts of the drawing that are revised and the parts that are not revised) and the revision number and description of the revision will be included on the drawing.;
(c) All all revisions on print media will be initialled by hand by the individual designer, design checker and, where applicable, by responsible for the drafter and the drafting checker submittal and will identify the individuals person who initialled the Operating Period Submittal. Electronic versions of the an Operating Period Submittal will identify the individuals persons who initialled the revisions to the printed version of the Operating Period Submittal.; and
(d) Project Co will keep all Reviewed Drawings and Specifications "REVIEWED" Operating Period Submittals are kept current. If any Reviewed Drawings and Specifications "REVIEWED" Operating Period Submittals are revised as part of a Submittalrevised, all other Reviewed Drawings and Specifications "REVIEWED" Operating Period Submittals relying on or based on that Reviewed Drawings and Specifications "REVIEWED" Operating Period Submittal will also be revised accordingly. All such revised Reviewed Drawings and Specifications "REVIEWED" Operating Period Submittals will also be submitted with the Operating Period Submittal to which it relates.
Appears in 1 contract
Sources: Operating Period Review Procedures