Schedule Management. 7.7.4.1. The RPR shall review the baseline, the projected, and the monthly construction progress schedules submitted by the contractor. The RPR shall monitor the progress of the work completed relative to the planned progress and address any identified schedule delays by emailing the EOR, NBU, and the contractor promptly.
Appears in 4 contracts
Sources: Professional Services, Professional Services, Professional Services
Schedule Management. 7.7.4.16.6.4.1. The RPR shall review the baseline, the projected, and the monthly construction progress schedules submitted by the contractor. The RPR shall monitor the progress of the work completed relative to the planned progress and address any identified schedule delays by emailing the EOR, NBU, and the contractor promptly.
Appears in 1 contract
Sources: Professional Services