Schedule Submittal Sample Clauses

The Schedule Submittal clause requires a contractor or project participant to provide a detailed timeline outlining the sequence and timing of project activities. Typically, this involves submitting a project schedule for approval before work begins, and may require updates if there are significant changes or delays. This clause ensures that all parties have a clear understanding of project milestones and deadlines, helping to coordinate efforts and manage expectations throughout the project.
Schedule Submittal. As stated above, the Contractor must, within 30 calendar days after the award, submit a complete schedule of operations to the Engineer. Acceptance of the Contractor’s Schedule as meeting the requirements of this subsection and the mobilization item shall not be construed to imply approval of any particular method or sequence of construction or to relieve the Contractor of providing sufficient materials, equipment and labor to guarantee completion of the project in accordance with the contract proposal, plans and specifications. Nor shall acceptance be construed to modify or amend the agreement or the date of completion therein. Schedules deviating from the Schedule and Suspension of Work requirements of the contract are unacceptable, unless the Contractor has made application in a separate writing and received written approval of the requested change, and if such a schedule is inadvertently “approved” that “approval” will be invalid. Contractor requests for alternative scheduling to that outlined on the Plan Staging/Phasing and the Schedule and Suspension of Work requirements in this proposal, will be entertained as a request for a waiver of specifications. Bids shall be based upon the scheduling and phasing in the bidding documents.
Schedule Submittal. As stated above, the Contractor must, within 30 calendar days after the award, submit a complete schedule of operations to the Engineer. Acceptance of the Contractor’s Schedule as meeting the requirements of this subsection and the mobilization item
Schedule Submittal. As stated above, the Contractor must, within 30 calendar days after the award, submit a complete schedule (Baseline Schedule @ Award) of operations to the Engineer. A Narrative Report shall also be submitted with each schedule submittal. The narrative report shall include an overall summary of the project and schedule, including and not limited to a description of the approach to performing the work, description of potential problem areas and potentials for delay, mandated contract dates including calendars with contractual non-work holidays, and other pertinent aspects related to the schedule. Acceptance of the Contractor’s Schedule as meeting the requirements of this subsection and the mobilization item shall not be construed to imply approval of any particular method or sequence of construction or to relieve the Contractor of providing sufficient materials, equipment and labor to guarantee completion of the project in accordance with the contract proposal, plans and specifications. Nor shall acceptance be construed to modify or amend the agreement or the date of completion therein. Schedules deviating from the Schedule and Suspension of Work requirements of the contract are unacceptable, unless the Contractor has made application in a separate writing and received written approval of the requested change, and if such a schedule is inadvertently “approved” that “approval” will be invalid. Contractor requests for alternative scheduling to that outlined on the Plan Staging/Phasing and the Schedule and Suspension of Work requirements in this proposal, will be entertained as a request for a waiver of specifications. Bids shall be based upon the scheduling and phasing in the bidding documents.
Schedule Submittal. As stated above, the Contractor must, within 30 calendar days after the award, submit a complete schedule of operations to the Engineer. Acceptance of the Contractor’s Schedule as meeting the requirements of this subsection and the mobilization item shall not be construed to imply approval of any particular method or sequence of construction or to relieve the Contractor of providing sufficient materials, equipment and labor to guarantee completion of the project in accordance with the contract proposal, plans and specifications. Nor shall acceptance be construed to modify or amend the agreement or the date of completion therein. Schedules deviating from the Schedule and Suspension of Work requirements of the

Related to Schedule Submittal

  • Submittal Schedule Within sixty days after the Effective Date of the Contract, the Contractor shall prepare and submit a Submittal Schedule for review and approval of the Design Professional. In establishing the Submittal Schedule the Contractor shall take into account large submittal documents that will require longer review times, e.g., submittals with over fifty sheets of drawings. The Design Professional’s approval shall be based on conformance of the Submittal Schedule with the Overall Project Schedule, subject to change from time to time in accordance with the progress of the Work.

  • BACKGROUND STATEMENT NCR Voyix and Customer agree that this Agreement will apply to: (a) the subscription licensing to Customer of Software at selected Customer sites and Hosted Software accessed via the internet; (b) the subscription or purchase of Equipment by Customer; and (c) NCR Voyix’s maintenance and support services, if any, for such Software and Equipment, as well as certain other services as set forth herein. Payment processing services are not covered by this Agreement. If NCR Voyix provides payment processing services as part of a Product bundle or otherwise, then such processing services will be covered by separate agreement.

  • WHO WILL REVIEW THE INFORMATION DISCLOSED ON THE RELATIONSHIP DISCLOSURE FORM AND ANY UPDATES?

  • Claims Submission We will submit your claims and assist you in any way we reasonably can to help get your claims paid. Your insurance company may need you to supply certain information directly. It is your responsibility to comply with their request. Please be aware that the balance of your claim is your responsibility whether or not your insurance company pays your claim. Your insurance benefit is a contract between you and your insurance company; we are not party to that contract.

  • Submitting Loop Makeup Service Inquiries 2.6.2.1 Comcast Phone may obtain LMU information by submitting a mechanized LMU query or a Manual LMUSI. Mechanized LMUs should be submitted through BellSouth's OSS interfaces. After obtaining the Loop information from the mechanized LMU process, if Comcast Phone needs further Loop information in order to determine Loop service capability, Comcast Phone may initiate a separate Manual Service Inquiry for a separate nonrecurring charge as set forth in Exhibit A of this Attachment. 2.6.2.2 Manual LMUSIs shall be submitted according to the guidelines in the LMU CLEC Information Package, incorporated herein by reference, as it may be amended from time to time, which can be found at the following BellSouth website: ▇▇▇▇://▇▇▇▇▇▇▇▇▇▇▇▇▇▇▇.▇▇▇▇▇▇▇▇▇.▇▇▇/guides/html/unes.html . The service interval for the return of a Manual LMUSI is three (3) business days. Manual LMUSIs are not subject to expedite requests. This service interval is distinct from the interval applied to the subsequent service order.