Scope Management. During the period of this contract the XipLink shall notify the Gogo Program Manager, in writing, of any activity that is requested that is not covered in the stated requirements for this work scope. If the Gogo Program Manager determines that the work activity is outside the scope of this contract, then further discussions will be held to clearly define the new requirements and its impact to schedule and cost. If appropriate, this statement of work will be amended to address the work scope change. No payment will be made for activities performed outside of the scope of this SOW without prior written consent of the Gogo Program Manager and the XipLink Program Manager.