Scope of Interconnection Facilities Study Clause Samples

The "Scope of Interconnection Facilities Study" clause defines the range and objectives of the study conducted to assess the requirements for connecting a new facility or project to an existing network or grid. This clause typically outlines what aspects will be analyzed, such as technical specifications, necessary upgrades, and cost estimates for the interconnection. For example, it may specify that the study will evaluate the impact of the new connection on system reliability and identify any modifications needed to accommodate the interconnection. Its core practical function is to ensure that all parties have a clear understanding of what the study will cover, thereby preventing misunderstandings and facilitating efficient planning and implementation of the interconnection process.
Scope of Interconnection Facilities Study. The Interconnection Facilities Study shall specify and estimate the cost of the equipment, engineering, procurement and construction work needed to implement the conclusions of the Interconnection System Impact Study in accordance with Good Utility Practice to physically and electrically connect the Interconnection Facility to the Transmission System. The Interconnection Facilities Study shall also identify the electrical switching configuration of the connection equipment, including, without limitation: the transformer, switchgear, meters, and other station equipment; the nature and estimated cost of any Transmission Provider's Interconnection Facilities and Network Upgrades necessary to accomplish the interconnection; and an estimate of the time required to complete the construction and installation of such facilities.
Scope of Interconnection Facilities Study. The Interconnection Facilities Study shall specify and provide a non-binding estimate of the cost of the equipment, engineering, procurement and construction work needed to implement the conclusions of the final Phase 2 or Phase 3 Report (as appropriate) in the Definitive Interconnection Study Process, the Replacement Impact Study and the Reliability Assessment Study in the Generation Replacement process, and the System Impact Study in the Serial Interconnection Study Process in accordance with Good Utility Practice to physically and electrically connect the Interconnection Facilities to the Transmission System. The Interconnection Facilities Study shall also identify the electrical switching configuration of the connection equipment, including, without limitation: the transformer, switchgear, meters, and other station equipment; the nature and estimated cost of any Transmission Provider's Interconnection Facilities and Network Upgrades necessary to accomplish the interconnection; and an estimate of the time required to complete the construction and installation of such facilities. The Interconnection Facilities Study will also identify any potential control equipment for requests for Interconnection Service that are lower than the Generating Facility Capacity.
Scope of Interconnection Facilities Study. The Interconnection Facilities Study shall specify and estimate the cost of the equipment, engineering, procurement and construction work needed to implement the conclusions of the Interconnection System Impact Study in accordance with Good Utility Practice to physically and electrically connect the Generating Facility to the Transmission System, including any Network Upgrades identified as necessary in the Interconnection System Impact Studies or studies pursuant to a Transmission Service Request. The Interconnection Facilities Study shall also identify the electrical switching configuration of the connection equipment, including, without limitation: the transformer, switchgear, meters, and other station equipment; the nature and estimated cost of any Transmission Provider Interconnection Facilities and any Network Upgrades necessary to accomplish the interconnection, and for an Interconnection Request in conjunction with a Transmission Service Request, capacity for transmission service; and an estimate of the time required to complete the construction and installation of such facilities. Transmission Provider will not perform an Interconnection Facilities Study for more than one generating output level. 8.2.1 If Interconnection Customer has submitted a Transmission Service Request in conjunction with its Interconnection Request as set forth in 8.1(c)(ii), Transmission Provider may perform a consolidated Facilities Study or concurrent Interconnection Facilities Study and Tariff facilities study that address the results of the Interconnection System Impact Study and the Tariff facilities study.
Scope of Interconnection Facilities Study. Upon receipt of an executed Interconnection Facilities Study Agreement and payment of the estimated cost to perform the Interconnection Facilities Study, an Interconnection Facilities Study will be carried out by, or on behalf of, the Transmission Provider and the Transmission Provider or ITC, as applicable, shall use Reasonable Efforts to coordinate the Interconnection Facilities Study with any affected adjacent regional transmission organizations, transmission owners, and local distribution utilities to determine the work required to effect the physical and electrical connection of the proposed Facility at the Point of Interconnection and to address, in accordance with Good Utility Practice, reliability problems identified in
Scope of Interconnection Facilities Study. ‌ The Interconnection Facilities Study shall specify and estimate the cost of the equipment, engineering, procurement and construction work needed to implement the conclusions of the Interconnection System Impact Study report in accordance with Good Utility Practice and NERC/WECC reliability standards set forth in Section 13.7 to physically and electrically connect the Interconnection Facilities to the Transmission System. The Interconnection Facilities Study shall also identify the electrical switching configuration of the connection equipment, including, without limitation: the transformer, switchgear, meters, and other station equipment; the nature and estimated cost of any Transmission Provider's Interconnection Facilities and Network Upgrades necessary to accomplish the interconnection; and an estimate of the time required to complete the construction and installation of such facilities.
Scope of Interconnection Facilities Study. The Interconnection Facilities Study shall be specific to each Interconnection Request and performed on an individual, i.e., non-clustered, basis. The Interconnection Facilities Study shall specify and provide a non-binding estimate the cost the equipment, engineering, procurement and construction work needed to implement the conclusions of the Cluster Study Report (and any associated restudies) in accordance with Good Utility Practice to physically and electrically connect the Interconnection Facilities to the Transmission System. The Interconnection Facilities Study shall also identify the electrical switching configuration of the connection equipment, including, without limitation: the transformer, switchgear, meters, and other station equipment; the nature and estimated cost of any Transmission Provider’s Interconnection Facilities and Network Upgrades necessary to accomplish the interconnection; and an estimate of the time required to complete the construction and installation of such facilities. The Interconnection Facilities Study will also identify any potential control equipment for (1) requests for Interconnection Service that are lower than the Generating Facility Capacity, and/or (2) requests to study a Generating Facility that includes at least one electric storage resource using operating assumptions (i.e., whether the interconnecting Generating Facility will or will not charge at peak load) that reflect its proposed charging behavior, as requested by Interconnection Customer, unless Transmission Provider determines that Good Utility Practice, including Applicable Reliability Standards, otherwise require the use of different operating assumptions.
Scope of Interconnection Facilities Study. The Interconnection Facilities Study shall specify and provide a non-binding estimate of the cost of the equipment, engineering, procurement and construction work needed to implement the conclusions of the final Phase 2 or Phase 3 Report (as appropriate) in the Definitive Interconnection Study Process and the System Impact Study in the Serial Interconnection Study Process Interconnection System Impact Study in accordance with Good Utility Practice to physically and electrically connect the Interconnection Facilityies to the Transmission System. The Interconnection Facilities Study shall also identify the electrical switching configuration of the connection equipment, including, without limitation: the transformer, switchgear, meters, and other station equipment; the nature and estimated cost of any Transmission Provider's Interconnection Facilities and Network Upgrades necessary to accomplish the interconnection; and an estimate of the time required to complete the construction and installation of such facilities. The Facilities Study will also identify any potential control equipment for requests for Interconnection Service that are lower than the Generating Facility Capacity.
Scope of Interconnection Facilities Study. The Interconnection Facilities Studies for a Class Year of Developers, as that Class Year is determined in accordance with Attachment S of the NYISO OATT, shall be performed concurrently as a combined Interconnection Facilities Study for that Class Year to fulfill the requirements of this Section 30.8, and the requirements of the Annual Transmission Reliability Assessment and Class Year Deliverability Study called for by Attachment S. The combined Interconnection Facilities Study shall specify and estimate the cost of the equipment, engineering and design work, permitting, site acquisition, procurement and construction work and commissioning needed for the Class Year in accordance with Good Utility Practice and, for each of these cost categories, shall specify and estimate the cost of the work to be done at each substation and/or on each feeder to physically and electrically connect each Large Facility in the Class Year to the Transmission System. The combined Interconnection Facilities Study shall also identify the electrical switching configuration of the connection equipment, including, without limitation: the transformer, switchgear, meters, and other station equipment; the nature and estimated cost of any Connecting Transmission OwnersAttachment Facilities and any System Upgrade Facilities and, for Large Facilities seeking ▇▇▇▇, any System Deliverability Upgrades necessary to accomplish the interconnection of each Large Facility in the Class Year; and shall include a schedule showing the estimated time required to complete the engineering and design, permitting, site acquisition, procurement, construction, installation and commissioning phases of the Large Facility interconnection projects. The schedule shall contain major milestones to facilitate the tracking of the progress of each Large Facility interconnection project. 30.8.2.1 Following commencement of the activities described in this schedule, each Developer, that Developer’s Connecting Transmission Owner and each Affected Transmission Owner(s) shall report every other month on the progress of their respective activities to the NYISO and to each other. Such reports shall be in a format consistent with, and include the content required by, applicable ISO Procedures. In these bimonthly reports, each Developer and Connecting Transmission Owner and Affected Transmission Owner(s) shall report any material variance from earlier schedule estimates for their respective activities, and the reasons for ...

Related to Scope of Interconnection Facilities Study

  • Purpose of Interconnection Facilities Except as may be required by Applicable Laws and Regulations, or as otherwise agreed to among the Parties, the Interconnection Facilities shall be constructed for the sole purpose of interconnecting the Large Generating Facility to the Participating TO’s Transmission System and shall be used for no other purpose.

  • Interconnection Facilities 4.1.1 The Interconnection Customer shall pay for the cost of the Interconnection Facilities itemized in Attachment 2 of this Agreement. The NYISO, in consultation with the Connecting Transmission Owner, shall provide a best estimate cost, including overheads, for the purchase and construction of its Interconnection Facilities and provide a detailed itemization of such costs. Costs associated with Interconnection Facilities may be shared with other entities that may benefit from such facilities by agreement of the Interconnection Customer, such other entities, the NYISO, and the Connecting Transmission Owner. 4.1.2 The Interconnection Customer shall be responsible for its share of all reasonable expenses, including overheads, associated with (1) owning, operating, maintaining, repairing, and replacing its own Interconnection Facilities, and

  • Scope of Interconnection Service 1.3.1 The NYISO will provide Energy Resource Interconnection Service and Capacity Resource Interconnection Service to Interconnection Customer at the Point of Interconnection. 1.3.2 This Agreement does not constitute an agreement to purchase or deliver the Interconnection Customer’s power. The purchase or delivery of power and other services that the Interconnection Customer may require will be covered under separate agreements, if any, or applicable provisions of NYISO’s or Connecting Transmission Owner’s tariffs. The Interconnection Customer will be responsible for separately making all necessary arrangements (including scheduling) for delivery of electricity in accordance with the applicable provisions of the ISO OATT and Connecting Transmission Owner’s tariff. The execution of this Agreement does not constitute a request for, nor agreement to, provide Energy, any Ancillary Services or Installed Capacity under the NYISO Services Tariff or any Connecting Transmission Owner’s tariff. If Interconnection Customer wishes to supply or purchase Energy, Installed Capacity or Ancillary Services, then Interconnection Customer will make application to do so in accordance with the NYISO Services Tariff or Connecting Transmission Owner’s tariff.

  • Interconnection Customer’s Interconnection Facilities The Interconnection Customer shall design, procure, construct, install, own and/or control the Interconnection Customer’s Interconnection Facilities described in Appendix A at its sole expense.

  • Use of Interconnection Facilities by Third Parties 494950 9.9.1 Purpose of Interconnection Facilities 494950 9.9.2 Third Party Users. 50 9.10 Disturbance Analysis Data Exchange. 50 ARTICLE 10. MAINTENANCE 50 10.1 Participating TO Obligations. 50 10.2 Interconnection Customer Obligations. 50 10.3 Coordination 505051