Common use of Sections III Clause in Contracts

Sections III. A.1(a) and (b) of the Schedule to the Agreement are deleted in their entirety and replaced with the following: (a) The Project Implementing Entity shall monitor and evaluate the progress of its Respective Part of the Project and prepare Project Reports for its Respective Part of the Project in accordance with the provisions of Section 4.08 of the General Conditions and on the basis of the indicators agreed with the Association and set forth in Section III.A.1(b) of Schedule 2 to the Financing Agreement. Each such Project Report shall cover the period of six months, and shall be furnished to the Recipient not later two weeks after the end of the period covered by such report for incorporation and forwarding by the Recipient to the Association of the overall Project Report.”

Appears in 3 contracts

Sources: Project Agreement, Project Agreement, Project Agreement