Setting Out. 11.1 The Contractor shall be responsible for the accurate setting-out of the Works in accordance with the Drawings, including lines, levels, positions, dimension, alignments, etc. of all parts of the Works. 11.2 Bench marks shall be established by UNICEF at all sites, and shall be available for the setting out. The Contractor shall be responsible for maintaining and protecting the bench marks at all times. 11.3 If at any time during the execution of the Works errors are found in this setting-out, the Contractor shall, at his own cost, rectify such error to the satisfaction of UNICEF.
Appears in 5 contracts
Sources: Construction Contract, Construction Contract, Contract for Construction Works
Setting Out. 11.1 The Contractor shall be responsible for the accurate setting-setting- out of the Works in accordance with the Drawings, including lines, levels, positions, dimension, alignments, etc. of all parts of the Works.
11.2 Bench marks shall be established by UNICEF at all sites, and shall be available for the setting out. The Contractor shall be responsible for maintaining and protecting the bench marks at all times.
11.3 If at any time during the execution of the Works errors are found in this setting-out, the Contractor shall, at his own cost, rectify such error to the satisfaction of UNICEF.
Appears in 1 contract