Common use of Shutdown Clause in Contracts

Shutdown. The unit will undertake a normal fired shutdown, where load is ramped down to a minimum. Then the 138kV GSU breaker associated with feeder 34126 will be opened first. After the 138kV GSU breaker associated with feeder 34126 is open, either one of the 138kV GSU breaker associated with feeder 34127 and 34129 will be open followed by opening of the generator circuit breaker (“GCB”). If neither of two feeders 34127 and 34129 is available and the Large Generating Facility delivers power to Astoria East Substation though single feeder 34126, the load will be ramped down to a minimum and then the GCB will be opened.

Appears in 4 contracts

Sources: Interconnection Agreement, Interconnection Agreement, Interconnection Agreement