Site Control. Documentation of site control must be submitted with the Interconnection Request. Site control may be demonstrated through: 32.1.5.1 Ownership of, a leasehold interest in, or a right to develop a site for the purpose of constructing the Small Generating Facility; 32.1.5.2 An option to purchase or acquire a leasehold site for such purpose; or 32.1.5.3 An exclusivity or other business relationship between the Interconnection Customer and the entity having the right to sell, lease, or grant the Interconnection Customer the right to possess or occupy a site for such purpose.
Appears in 6 contracts
Sources: Transmission Wheeling Agreements, Open Access Transmission Tariff (Oatt), Small Generator Interconnection Procedures
Site Control. Documentation of site control must be submitted with the Interconnection Request. Site control may be demonstrated through:
32.1.5.1 1.5.1 Ownership of, a leasehold interest in, or a right to develop a site for the purpose of constructing the Small Generating Facility;
32.1.5.2 1.5.2 An option to purchase or acquire a leasehold site for such purpose; or
32.1.5.3 1.5.3 An exclusivity or other business relationship between the Interconnection Customer and the entity having the right to sell, lease, or grant the Interconnection Customer the right to possess or occupy a site for such purpose.
Appears in 3 contracts
Sources: Small Generator Interconnection Agreement, Standard Small Generator Interconnection Agreement, Standard Small Generator Interconnection Agreement (Sgia)
Site Control. Documentation of site control must be submitted with the Interconnection Request. Site control may be demonstrated through:
32.1.5.1 1.5.1 Ownership of, a leasehold interest in, or a right to develop a site for the purpose of constructing the Small Generating Facility;
32.1.5.2 1.5.2 An option to purchase or acquire a leasehold site for such purpose; or
32.1.5.3 1.5.3 An exclusivity or other business relationship between the Interconnection Customer and the entity having the right to sell, lease, or grant the Small Generator Interconnection Procedures (SGIP) 3 Interconnection Customer the right to possess or occupy a site for such purpose.
Appears in 1 contract
Sources: Standard Small Generator Interconnection Agreement (Sgia)
Site Control. Documentation of site control must be submitted with the Interconnection Request. Site control may be demonstrated through:
32.1.5.1 1.5.1 Ownership of, a leasehold interest in, or a right to develop a site for the purpose of constructing the Small Generating Facility;
32.1.5.2 1.5.2 An option to purchase or acquire a leasehold site for such purpose; or
32.1.5.3 1.5.3 An exclusivity or other business relationship between the Interconnection Customer and the entity having the right to sell, lease, or grant the Interconnection Customer the right to possess or occupy a site for such purpose.
Appears in 1 contract
Sources: Standard Small Generator Interconnection Agreement (Sgia)