Site Data. (i) The Contractor shall be deemed to have inspected and examined the Site and its Page 40 of 159 surroundings and to have satisfied himself before entering into the Agreement in all material respects including but not limitedto: (a) the form and nature of the Site (including, inter-alia, the surface and sub- surface conditions and geo-technicalfactors); (b) the hydrological and climaticconditions; (c) the extent and nature of the works already completed and Materials necessary for the execution and completion of the Works and the remedying of any defects that includes already executed partalso. (d) the suitability and the adequacy of the Site for the execution of theWorks; (e) the means of access to the Site and the accommodation the Contractor may require; (f) arranging permits as required as per [.] of theAgreement. (g) the requirements of operation and maintenance;and 4.12 all other factors and circumstances affecting the Contractor's rights and obligations under the Agreement, the Contract Price and Time forCompletion.Sufficiency of Contract Price
Appears in 1 contract
Sources: Contract Agreement
Site Data. (i) The Contractor shall be deemed to have inspected and examined the Site and its Page 40 of 159 surroundings and to have satisfied himself before entering into the Agreement in all material respects including but not limitedto:
(a) the form and nature of the Site (including, inter-alia, the surface and sub- surface conditions and geo-technicalfactors);
(b) the hydrological and climaticconditions;
(c) the extent and nature of the works already completed and Materials necessary for the execution and completion of the Works and the remedying of any defects that includes already executed partalso.
(d) the suitability and the adequacy of the Site for the execution of theWorks;
(e) the means of access to the Site and the accommodation the Contractor may require;
(f) arranging permits as required as per [.] of theAgreement.
(g) the requirements of operation and maintenance;and
4.12 (h) all other factors and circumstances affecting the Contractor's rights and obligations under the Agreement, the Contract Price and Time forCompletion.Sufficiency of Contract Price
Appears in 1 contract
Sources: Engineering Procurement and Construction (Epc) Agreement
Site Data. (i) The Contractor shall be deemed to have inspected and examined the Site and its Page 40 of 159 surroundings itssurroundings and to have satisfied himself before entering into the Agreement theAgreement in all material allmaterial respects including but not limitedtolimited to:
(a) the form and nature of the Site (including, inter-alia, the surface and sub- surface conditions subsurfaceconditions and geo-technicalfactorstechnical factors);
(b) the hydrological and climaticconditionsclimatic conditions;
(c) the extent and nature of the works already completed and Materials necessary for necessaryfor the execution and completion of the Works and the remedying of any defects anydefects that includes already executed partalsopart also.
(d) the suitability and the adequacy of the Site for the execution of theWorksthe Works;
(e) the means of access to the Site and the accommodation the Contractor may requiremayrequire;
(f) arranging permits as required as per [.] of theAgreementthe Agreement.
(g) the requirements of operation and maintenance;andmaintenance; and
4.12 (h) all other factors and circumstances affecting the Contractor's rights and obligations andobligations under the Agreement, the Contract Price and Time forCompletionfor Completion.Sufficiency of Contract Price