SITE WORKS. 3.1 Clear site of works of shrubs, bushes and trees m² 90 3.2 Excavate around foundation not exceeding 1m deep m³ 10 3.3 Excavate to remove top soil and load and cart away to contractors tipping site average depth 150mm m² 90 3.4 load and cart away surplus spoil to contractor’s dump site m³ 60 3.5 Backfill and compact in layers not exceeding 150mm m³ 90 3.6 Supply and install 500 gauge polythene laid under surface beds m² 90 3.7 Apply approved ant termite treatment m² 90
Appears in 1 contract
SITE WORKS. 3.1 Clear site of works of shrubs, bushes and trees m² 90
3.2 Excavate around foundation not exceeding 1m deep m³ 10 3.3 Excavate to remove top soil and load and cart away to contractors tipping site average depth 150mm m² 90
3.4 load and cart away surplus spoil to contractor’s dump site m³ 60
3.5 Backfill and compact in layers not exceeding 150mm m³ 90
3.6 Supply and install 500 gauge polythene laid under surface beds m² 90
90 3.7 Apply approved ant termite treatment m² 90
Appears in 1 contract