Sources of Payment. Notwithstanding the foregoing, Contractor shall not be required to implement any Change in the Work in excess of an aggregate value of NZ$25,000 (Twenty Five Thousand New Zealand Dollars) for all Changes in the Work until adequate assurances have been provided to Contractor by Owner of sources of payment by means acceptable to Contractor to pay for any increased costs and any extensions in time.
Appears in 2 contracts
Sources: Engineering, Procurement and Construction Contract (Ormat Technologies, Inc.), Engineering, Procurement and Construction Contract (Ormat Technologies, Inc.)