Common use of Special Protection Systems Clause in Contracts

Special Protection Systems. The Generator shall ensure that the Generation Rejection Scheme(s) as required by the IESO in their System Impact Assessment (SIA) have been successfully installed, tested and commissioned before connecting to GLP system. The Generator will inform GLPL 30 days prior to commissioning of the Generation Rejection Schemes and GLP will retain the right to witness the testing and commissioning to confirm satisfactory performance of such systems at the sole discretion of GLP. By (insert date), the Generator will have commissioned the Generation Rejection Scheme(s).

Appears in 2 contracts

Sources: Connection and Cost Recovery Agreement, Connection and Cost Recovery Agreement