Specification Engineering and Other Changes. 8.1 Engineering Design Changes. All engineering changes and sourcing changes must be approved by SSE before implementation by FIC. FIC will advise SSE within [*], how soon and at what cost, engineering changes can be implemented. The cost increases or decreases incurred as a result of engineering and/or 6 sourcing changes will be reviewed and an equitable adjustment shall be made in the unit price of such effected Product Units, or shipping schedule or both, including increased or decreased costs to FIC, as approved by SSE, for any material that is rendered excess and/or obsolete pursuant to Section 6 above, due to such engineering change. Such engineering change will be implemented only upon receipt by FIC of SSE's written request to proceed with the change, provided however that SSE and FIC will mutually agree upon the effective date of the change.