Starting and Completion. 30.1 The Supplier does not start work until the starting date and does the work so that Completion is on or before the Completion Date. 30.2 The Employer decides the date of Completion and certifies it within one week of the date. 30.3 The Employer may instruct the Supplier to stop or not to start any work and may later instruct him that he may restart or start it.
Appears in 3 contracts
Sources: Nec3 Term Service Short Contract (Tssc3), Nec3 Term Service Short Contract (Tssc3), Nec3 Term Service Short Contract