Substantial Completion Certificate. certifying that the construction of Landlord’s Section 2.3 Work has been substantially completed in accordance with this Section 2.3 and specifying the date of that completion. Thereafter, beginning on the Rent Commencement Date and continuing during the rest of the term of this Lease, Tenant shall be responsible (subject, however, to any corrective obligations of Landlord as expressly set forth in this Lease) for maintenance, repair and/or replacement of all such systems and improvements to the extent required under the provisions of Article 8 hereof. If Landlord’s obligations under this paragraph are violated in any respect, then it shall be the obligation of Landlord, after receipt of written notice from Tenant setting forth with specificity the nature of the violation, to correct promptly and diligently, at Landlord’s sole cost, the condition(s) constituting such violation. However, in the case of the requirements set forth in clause (i) of the first sentence of this paragraph, Tenant’s failure to give such written notice to Landlord within six (6) months after the Rent Commencement Date shall give rise to a conclusive and irrebuttable presumption that Landlord has complied with all Landlord’s obligations under such clause (i), and in the case of the requirements set forth in clauses (ii) through (v) of the first sentence of this paragraph (except with respect to latent defects in the case of the requirements set forth in clauses (iii) and (v) of the first sentence of this paragraph), Tenant’ failure to give such written notice to Landlord regarding any alleged violation within one (1) year after the Rent Commencement Date shall give rise to a conclusive and irrebuttable presumption that Landlord has complied with all Landlord’s obligations under such clauses (ii) through (v). TENANT ACKNOWLEDGES THAT THE WARRANTIES AND/OR OBLIGATIONS CONTAINED IN THIS SECTION 2.3 AND IN THE WORKLETTER (IF APPLICABLE) ARE IN LIEU OF ALL OTHER WARRANTIES, EXPRESS OR IMPLIED, WITH RESPECT TO THE PHYSICAL CONDITION OF THE PREMISES, BUILDING SYSTEMS AND EXISTING IMPROVEMENTS (OTHER THAN TENANT IMPROVEMENTS) IN THE PREMISES, AND THAT LANDLORD MAKES NO OTHER WARRANTIES EXCEPT AS EXPRESSLY SET FORTH IN THIS SECTION 2.3 AND, IN THE CASE OF TENANT IMPROVEMENTS CONSTRUCTED BY LANDLORD UNDER THE WORKLETTER, AS EXPRESSLY SET FORTH IN THE WORKLETTER.
Appears in 3 contracts
Sources: Sublease (OncoMed Pharmaceuticals Inc), Sublease (OncoMed Pharmaceuticals Inc), Lease Agreement (OncoMed Pharmaceuticals Inc)
Substantial Completion Certificate. certifying (a) Project Co shall give the Independent Certifier and the CTC Representative at least ten Business Days’ notice prior to the date upon which Project Co anticipates delivering the Substantial Completion Notice.
(b) Project Co shall give the Independent Certifier and the CTC Representative notice (the “Substantial Completion Notice”) upon the satisfaction of all requirements for Substantial Completion, which Substantial Completion Notice shall describe, in reasonable detail, the satisfaction of the requirements for Substantial Completion, together with Project Co’s opinion as to whether the conditions for issuance of the Substantial Completion Certificate have been satisfied.
(c) The CTC shall, within five Business Days after receipt of the Substantial Completion Notice, provide the Independent Certifier and Project Co with the CTC’s opinion as to whether the conditions for issuance of the Substantial Completion Certificate have been satisfied and, if applicable, any reasons as to why it considers that the construction Substantial Completion Certificate should not be issued.
(d) Within five Business Days after Project Co’s receipt of Landlordthe CTC’s opinion pursuant to Section 2.3 Work has 24.4(c), the Parties shall cause the Independent Certifier to determine whether the conditions for issuance of the Substantial Completion Certificate have been substantially completed satisfied, having regard for the opinions of both Project Co and the CTC, to determine whether any Minor Deficiencies exist, and to issue to the CTC and to Project Co either:
(i) the Substantial Completion Certificate, confirming the date of issue as the Substantial Completion Date and setting out the Minor Deficiencies List (if applicable) in accordance with this Section 2.3 24.8; or
(ii) a report detailing the matters that the Independent Certifier considers are required to be performed by Project Co to satisfy the conditions for issuance of the Substantial Completion Certificate.
(e) Where the Independent Certifier has issued a report in accordance with Section 24.4(d)(ii) and specifying Project Co has not referred a Dispute in relation thereto for resolution in accordance with Schedule 27 – Dispute Resolution Procedure, Project Co shall, within 5 Business Days after receipt of such report, provide the date Independent Certifier and the CTC Representative with:
(i) a detailed list indicating the rectification actions proposed for all matters raised in such report;
(ii) the schedule for completion of all such rectification actions; and
(iii) any additional Project Co Commissioning that completionneeds to be undertaken as a result of the rectification actions, and Project Co shall perform all such additional rectification actions and Project Co Commissioning in a timely manner. ThereafterUpon completion thereof, beginning Project Co may give a further Substantial Completion Notice and Sections 24.4(c) to (e), inclusive, shall be repeated until the Substantial Completion Certificate has been issued.
(f) The Independent Certifier’s decision to issue or not to issue the Substantial Completion Certificate shall be final and binding on the Rent Commencement Parties solely in respect of determining the Substantial Completion Payment Date, and a Dispute in relation to the Substantial Completion Payment Date and continuing during shall not be subject to resolution pursuant to the rest of the term of this LeaseDispute Resolution Procedure, Tenant shall be responsible (subjectprovided, however, to that any corrective obligations of Landlord as expressly set forth other Dispute in this Lease) for maintenance, repair and/or replacement of all such systems and improvements relation to the extent required under Independent Certifier’s decision to issue or not to issue the provisions of Article 8 hereof. If Landlord’s obligations under this paragraph are violated Substantial Completion Certificate may be referred for resolution pursuant to the Schedule 27 – Dispute Resolution Procedure.
(g) Project Co shall provide As-Built Drawings and specifications, Design Data, spare parts and Shop Drawings as soon as possible and in any respect, then it shall be the obligation of Landlord, after receipt of written notice from Tenant setting forth with specificity the nature of the violation, to correct promptly and diligently, at Landlord’s sole cost, the condition(s) constituting such violation. However, in the case of the requirements set forth in clause (i) of the first sentence of this paragraph, Tenant’s failure to give such written notice to Landlord within six (6) months event no later than 30 days after the Rent Commencement Date shall give rise to a conclusive and irrebuttable presumption that Landlord has complied with all Landlord’s obligations under such clause (i), and in the case of the requirements set forth in clauses (ii) through (v) of the first sentence of this paragraph (except with respect to latent defects in the case of the requirements set forth in clauses (iii) and (v) of the first sentence of this paragraph), Tenant’ failure to give such written notice to Landlord regarding any alleged violation within one (1) year after the Rent Commencement Date shall give rise to a conclusive and irrebuttable presumption that Landlord has complied with all Landlord’s obligations under such clauses (ii) through (v). TENANT ACKNOWLEDGES THAT THE WARRANTIES AND/OR OBLIGATIONS CONTAINED IN THIS SECTION 2.3 AND IN THE WORKLETTER (IF APPLICABLE) ARE IN LIEU OF ALL OTHER WARRANTIES, EXPRESS OR IMPLIED, WITH RESPECT TO THE PHYSICAL CONDITION OF THE PREMISES, BUILDING SYSTEMS AND EXISTING IMPROVEMENTS (OTHER THAN TENANT IMPROVEMENTS) IN THE PREMISES, AND THAT LANDLORD MAKES NO OTHER WARRANTIES EXCEPT AS EXPRESSLY SET FORTH IN THIS SECTION 2.3 AND, IN THE CASE OF TENANT IMPROVEMENTS CONSTRUCTED BY LANDLORD UNDER THE WORKLETTER, AS EXPRESSLY SET FORTH IN THE WORKLETTERSubstantial Completion Date.
Appears in 2 contracts
Sources: Project Agreement, Project Agreement
Substantial Completion Certificate. certifying (a) Project Co shall give the Independent Certifier and the SJHC Representative at least 10 Business Days’ notice prior to the date upon which Project Co anticipates all requirements for Substantial Completion shall be satisfied.
(b) Project Co shall give the Independent Certifier and the SJHC Representative notice (the “Substantial Completion Notice”) upon the satisfaction of all requirements for Substantial Completion, which Substantial Completion Notice shall describe, in reasonable detail, the satisfaction of the requirements for Substantial Completion, together with Project Co’s opinion as to whether the conditions for issuance of the Substantial Completion Certificate have been satisfied.
(c) SJHC shall, within 5 Business Days after receipt of the Substantial Completion Notice, provide the Independent Certifier and Project Co with SJHC’s opinion as to whether the conditions for issuance of the Substantial Completion Certificate have been satisfied and, if applicable, any reasons as to why it considers that the construction Substantial Completion Certificate should not be issued.
(d) Within 5 Business Days after Project Co’s receipt of LandlordSJHC’s opinion pursuant to Section 2.3 Work has 24.4(c), the Parties shall cause the Independent Certifier to determine whether the conditions for issuance of the Substantial Completion Certificate have been substantially completed satisfied, having regard for the opinions of both Project Co and SJHC, to determine whether any Minor Deficiencies exist, and to issue to SJHC and to Project Co either:
(i) the Substantial Completion Certificate, setting out in such certificate the Substantial Completion Date and the Minor Deficiencies List (if applicable) in accordance with this Section 2.3 24.8; or
(ii) a report detailing the matters that the Independent Certifier considers are required to be performed by Project Co to satisfy the conditions for issuance of the Substantial Completion Certificate.
(e) Where the Independent Certifier has issued a report in accordance with Section 24.4(d)(ii) and specifying Project Co has not referred a Dispute in relation thereto for resolution in accordance with Schedule 27 - Dispute Resolution Procedure, Project Co shall, within 5 Business Days after receipt of such report, provide the date Independent Certifier and the SJHC Representative with:
(i) a detailed list indicating the rectification actions proposed for all matters raised in such report;
(ii) the schedule for completion of all such rectification actions; and
(iii) any additional Project Co Commissioning that completionneeds to be undertaken as a result of the rectification actions, and Project Co shall perform all such additional rectification actions and Project Co Commissioning in a timely manner. ThereafterUpon completion thereof, beginning Project Co may give a further Substantial Completion Notice and Sections 24.4(c) to (e), inclusive, shall be repeated until the Substantial Completion Certificate has been issued.
(f) The Independent Certifier’s decision to issue or not to issue the Substantial Completion Certificate shall be final and binding on the Rent Parties solely in respect of determining the Payment Commencement Date, and a Dispute in relation to the Payment Commencement Date and continuing during shall not be subject to resolution pursuant to the rest of the term of this LeaseDispute Resolution Procedure, Tenant shall be responsible (subjectprovided, however, to that any corrective obligations of Landlord as expressly set forth other Dispute in this Lease) for maintenance, repair and/or replacement of all such systems and improvements relation to the extent required under Independent Certifier’s decision to issue or not to issue the provisions of Article 8 hereof. If Landlord’s obligations under this paragraph are violated in any respect, then it shall Substantial Completion Certificate may be referred for resolution pursuant to the obligation of Landlord, after receipt of written notice from Tenant setting forth with specificity the nature of the violation, to correct promptly and diligently, at Landlord’s sole cost, the condition(s) constituting such violation. However, in the case of the requirements set forth in clause (i) of the first sentence of this paragraph, Tenant’s failure to give such written notice to Landlord within six (6) months after the Rent Commencement Date shall give rise to a conclusive and irrebuttable presumption that Landlord has complied with all Landlord’s obligations under such clause (i), and in the case of the requirements set forth in clauses (ii) through (v) of the first sentence of this paragraph (except with respect to latent defects in the case of the requirements set forth in clauses (iii) and (v) of the first sentence of this paragraph), Tenant’ failure to give such written notice to Landlord regarding any alleged violation within one (1) year after the Rent Commencement Date shall give rise to a conclusive and irrebuttable presumption that Landlord has complied with all Landlord’s obligations under such clauses (ii) through (v). TENANT ACKNOWLEDGES THAT THE WARRANTIES AND/OR OBLIGATIONS CONTAINED IN THIS SECTION 2.3 AND IN THE WORKLETTER (IF APPLICABLE) ARE IN LIEU OF ALL OTHER WARRANTIES, EXPRESS OR IMPLIED, WITH RESPECT TO THE PHYSICAL CONDITION OF THE PREMISES, BUILDING SYSTEMS AND EXISTING IMPROVEMENTS (OTHER THAN TENANT IMPROVEMENTS) IN THE PREMISES, AND THAT LANDLORD MAKES NO OTHER WARRANTIES EXCEPT AS EXPRESSLY SET FORTH IN THIS SECTION 2.3 AND, IN THE CASE OF TENANT IMPROVEMENTS CONSTRUCTED BY LANDLORD UNDER THE WORKLETTER, AS EXPRESSLY SET FORTH IN THE WORKLETTERDispute Resolution Procedure.
Appears in 1 contract
Sources: Project Agreement
Substantial Completion Certificate. certifying that the construction of Landlord’s Section 2.3 Work has been substantially completed in accordance with this Section 2.3 and specifying the date of that completion. , Thereafter, beginning on the Rent Commencement Date and continuing during the rest of the term of this Lease, Tenant shall be responsible (subject, however, to any corrective obligations of Landlord as expressly set forth in this Lease) for maintenance, repair and/or replacement of all such systems and improvements to the extent required under the provisions of Article 8 hereof. If Landlord’s obligations under this paragraph are violated in any respect, then it shall be the obligation of Landlord, after receipt of written notice from Tenant setting forth with specificity the nature of the violation, to correct promptly and diligently, at Landlord’s sole cost, the condition(scondition (s) constituting such violation. However, in the case of the requirements set forth in clause (i) of the first sentence of this paragraph, Tenant’s failure to give such written notice to Landlord within six (6) months after the Rent Commencement Date shall give rise to a conclusive and irrebuttable presumption that Landlord has complied with all Landlord’s obligations under such clause (i), and in the case of the requirements set forth in clauses (ii) through (v) of the first sentence of this paragraph (except with respect to latent defects in the case of the requirements set forth in clauses (iii) and (v) of the first sentence of this paragraph), Tenant’ failure to give such written notice to Landlord regarding any alleged violation within one (1) year after the Rent Commencement Date shall give rise to a conclusive and irrebuttable presumption that Landlord has complied with all Landlord’s obligations under such clauses (ii) through (v). TENANT ACKNOWLEDGES THAT THE WARRANTIES AND/OR OBLIGATIONS CONTAINED IN THIS SECTION 2.3 AND IN THE WORKLETTER (IF APPLICABLE) ARE IN LIEU OF ALL OTHER WARRANTIES, EXPRESS OR IMPLIED, WITH RESPECT TO THE PHYSICAL CONDITION OF THE PREMISES, BUILDING SYSTEMS AND EXISTING IMPROVEMENTS (OTHER THAN TENANT IMPROVEMENTS) IN THE PREMISES, AND THAT LANDLORD MAKES NO OTHER WARRANTIES EXCEPT AS EXPRESSLY SET FORTH IN THIS SECTION 2.3 AND, IN THE CASE OF TENANT IMPROVEMENTS CONSTRUCTED BY LANDLORD UNDER THE WORKLETTER, AS EXPRESSLY SET FORTH IN THE WORKLETTER.
Appears in 1 contract