Substantial Completion Certificate. 13.1.1 The Concessionaire will issue to the Independent Certifier and the Province’s Representative a notice informing the Independent Certifier and the Province’s Representative at least 20 Working Days prior to the date upon which the Concessionaire expects the Works will be Substantially Completed. If the Concessionaire has at any time reason to believe that the said date expected for Substantial Completion as aforesaid will be delayed by more than 5 Working Days, it will issue a fresh notice pursuant to this Section 13.1.1 informing the Independent Certifier and the Province’s Representative of the new date expected for Substantial Completion as aforesaid. Upon the Concessionaire notifying the Independent Certifier and the Province’s Representative that Substantial Completion as aforesaid has occurred and subject to the delivery to the Independent Certifier and the Province’s Representative of a Concessionaire’s Substantial Completion Certificate and all other relevant Certificates and supporting documentation in accordance with Part 3 of Schedule 5 [Design and Certification Procedure], the Province’s Representative and the Concessionaire will cause the Independent Certifier to commence within 10 Working Days of receipt of such notice an inspection of the Works (and the Concessionaire will not object to any Interested Party, any Public Authority to whom any Temporary Off-Site Facilities are to be handed over and/or any contractors or consultants retained by the Province or any such Interested Party which has a legal obligation or right to inspect the Works or Public Authority participating in such inspection). 13.1.2 The Province’s Representative and the Concessionaire’s Representative will cause the Independent Certifier within 20 Working Days of the commencement of such inspection to either:
Appears in 2 contracts
Sources: Concession Agreement, Concession Agreement