Common use of SUBSTANTIAL PERFORMANCE OF THE WORK Clause in Contracts

SUBSTANTIAL PERFORMANCE OF THE WORK. AND PAYMENT OF HOLDBACK 5.4.1 When the Contractor considers that Substantial Performance of the Work has been achieved, the Contractor shall prepare and submit to the Consultant and the Owner a comprehensive deficiency list of items to be completed or corrected, including any incomplete Close-Out Documentation, and apply for a review by the Consultant and the Owner to establish Substantial Performance of the Work. Failure to include an item on the list does not alter the responsibility of the Contractor to complete the Contract.

Appears in 3 contracts

Sources: Supplementary Conditions to Ccdc2 – 2020 Version, Supplementary Conditions to CCDC 2 – 2020 Version, Supplementary Conditions to Ccdc2 – 2020 Version