Common use of Substitution Requests Clause in Contracts

Substitution Requests. 7.1 The CM will be responsible for logging all substitution requests. 7.2 The CM will be responsible for reviewing all substitution requests to insure that they are complete; and, if not, returning them to the Trade Contractor for proper submission. 7.3 The CM will be responsible to review all substitution or “or equal” requests prior to submission to the Project Designer and the OWNER. 7.4 The CM shall be responsible for tracking and monitoring all substitution requests throughout the Construction Phase until the Project Designer and/or the OWNER process all substitution requests. The CM shall be responsible to see that all substitution requests are submitted in a timely manner per the General Conditions. 7.5 The CM shall include substitution requests, if any, as an agenda topic at the OWNER's meetings and advise the OWNER immediately of any delays in the substitution request process.

Appears in 2 contracts

Sources: Construction Management Agreement, Construction Management Agreement