Synchronization. 6.2.1 The SPV shall give at least 30 (thirty) days written notice to the SLDC/MSEDCL, of the date on which it intends to synchronize the Unit(s) of the Project to the Grid System. 6.2.2 Subject to the provisions in this Article 6, each Unit will be synchronized by the SPV to the Grid System when it meets all the connection conditions prescribed in the Grid Code and otherwise meets all other requirements under Law for synchronization to the Grid System. 6.2.3 The synchronization equipment and all necessary arrangements/ equipment including ‘Remote Terminal Unit’ for scheduling of power generated from the Project and transmission of data to the concerned authority as per applicable regulation shall be installed by the SPV at its generation facility of the Project at its own cost. The SPV shall synchronize its system with the Grid System only after the approval of SLDC or MSEDCL. 6.2.4 Prior to synchronization of the Project, the SPV shall be required to get the Project certified for the requisite acceptance/performance test as may be laid down by respective authorities. 6.2.5 The SPV shall immediately after each synchronization / tripping of SPV, inform the sub-station of the Grid System to which the Project is electrically connected in accordance with applicable Grid Code. In addition, the SPV shall inject in-firm power from the Units to the grid from time to time to carry out operational/ functional test(s) prior to the Commercial Operation Date. For avoidance of doubt, it is clarified that synchronization / connection of the Project with the grid shall not to be considered as Commissioning of the Project. 6.2.6 Subsequent to grant of connectivity and after completion of each Unit in all aspects, a delay in grant of synchronization/charging permission by the STU and/or a delay in readiness of the MSEDCL/STU substation at the Delivery Point, including readiness of the power evacuation and transmission infrastructure of the STU network until Scheduled Commercial Operation Date of the Project, shall be treated as delays beyond the control of the SPV, provided that the following are established by the SPV: (a) Unit including its transmission line till STU’s substation has been completed by SPV and CEIG approval/certificate for the same has also been obtained by the SPV; (b) The SPV has adhered to all the applicable procedures and requirements in regard to ‘Connectivity and Synchronization’ of the Unit as notified by the MERC/STU; (c) The SPV has complied with the complete application formalities for connectivity within the timeline as prescribed under Law; and, (d) The SPV has complied with the complete application formalities for synchronization of the Unit at least 15 (fifteen) days prior to COD. 6.2.7 In the event of any delay as set out in Article 6.2.6 hereinabove, the Units that are impacted by such delay shall be deemed to have achieved the Commercial Operation Date on the Scheduled Commercial Operation Date. Such Units shall be eligible to receive Deemed Generation in terms of Article 7.5 hereinbelow until the event of delay set out in Article 6.2.6 hereinabove is remedied by MSEDCL. 6.2.8 Decision on eligibility for deemed achievement of Commercial Operation Date and receiving Deemed Generation on account of the above factor shall be taken by MSEDCL based on supporting documents and evidence available and provided by the SPV. In case of delay in Commissioning of a Unit due to reasons beyond the reasonable control of the SPV, MSEDCL may extend the Scheduled Commercial Operation Date after examining the issue on a case-to-case basis.
Appears in 16 contracts
Sources: Power Purchase Agreement, Power Purchase Agreement, Power Purchase Agreement
Synchronization. 6.2.1 The SPV shall give at least 30 (thirty) days written notice to the SLDC/MSEDCL, of the date on which it intends to synchronize the Unit(s) of the Project to the Grid System.
6.2.2 Subject to the provisions in this Article 6, each Unit will be synchronized by the SPV to the Grid System when it meets all the connection conditions prescribed in the Grid Code and otherwise meets all other requirements under Law for synchronization to the Grid System.
6.2.3 The synchronization equipment and all necessary arrangements/ equipment including ‘Remote Terminal Unit’ for scheduling of power generated from the Project and transmission of data to the concerned authority as per applicable regulation shall be installed by the SPV at its generation facility of the Project at its own cost. The SPV shall synchronize its system with the Grid System only after the approval of SLDC or MSEDCL.
6.2.4 Prior to synchronization of the Project, the SPV shall be required to get the Project certified for the requisite acceptance/performance test as may be laid down by respective authorities.
6.2.5 The SPV shall immediately after each synchronization / tripping of SPV, inform the sub-station of the Grid System to which the Project is electrically connected in accordance with applicable Grid Code. In addition, the SPV shall inject in-firm power from the Units to the grid from time to time to carry out operational/ functional test(s) prior to the Commercial Operation Date. For avoidance of doubt, it is clarified that synchronization / connection of the Project with the grid shall not to be considered as Commissioning of the Project.
6.2.6 Subsequent to grant of connectivity and after completion of each Unit in all aspects, a delay in grant of synchronization/charging permission by the STU and/or a delay in readiness of the MSEDCL/STU substation at the Delivery Point, including readiness of the power evacuation and transmission infrastructure of the STU network until Scheduled Commercial Operation Date of the Project, shall be treated as delays beyond the control of the SPV, provided that the following are established by the SPV:
(a) A Unit including its transmission line till MSEDCL / STU’s substation has been completed by SPV and CEIG approval/certificate for the same has also been obtained by the SPV;
(b) The SPV has adhered to all the applicable procedures and requirements in regard to ‘Connectivity and Synchronization’ of the Unit as notified by the MERC/STU;
(c) The SPV has complied with the complete application formalities for connectivity within the timeline as prescribed under Law; and,
(d) The SPV has complied with the complete application formalities for synchronization of the Unit at least 15 (fifteen) days prior to CODthe Commercial Operation Date.
6.2.7 In the event of any delay as set out in Article 6.2.6 hereinabove, the Units that are impacted by such delay shall be deemed to have achieved the Commercial Operation Date on the Scheduled Commercial Operation Date. Such Units shall be eligible to receive Deemed Generation in terms of Article 7.5 hereinbelow until the event of delay set out in Article 6.2.6 hereinabove is remedied by MSEDCL.
6.2.8 Decision on eligibility for deemed achievement of Commercial Operation Date and receiving Deemed Generation on account of the above factor shall be taken by MSEDCL based on supporting documents and evidence available and provided by the SPV. In case of delay in Commissioning of a Unit due to reasons beyond the reasonable control of the SPV, MSEDCL may extend the Scheduled Commercial Operation Date after examining the issue on a case-to-case basis.
Appears in 1 contract
Sources: Power Purchase Agreement
Synchronization. 6.2.1 The SPV shall give at least 30 (thirty) days written notice to the SLDC/MSEDCL, of the date on which it intends to synchronize the Unit(s) of the Project to the Grid System.
6.2.2 Subject to the provisions in this Article 6, each Unit will shall be synchronized by the SPV to the Grid System when it meets all the connection conditions prescribed in the Grid Code and otherwise meets all other requirements under Law for synchronization to the Grid System.
6.2.3 The synchronization equipment and all necessary arrangements/ equipment including ‘„Remote Terminal Unit’ Unit‟ for scheduling of power generated from the Project and transmission of data to the concerned authority as per applicable regulation shall be installed by the SPV at its generation facility of the Project at its own cost. The SPV shall synchronize its system with the Grid System only after the approval of SLDC or MSEDCL.
6.2.4 Prior to synchronization of the Project, the SPV shall be required to get the Project certified for the requisite acceptance/performance test as may be laid down by respective the concerned authorities.
6.2.5 The SPV shall immediately after each synchronization / tripping of SPV, inform the sub-station of the Grid System to which the Project is electrically connected in accordance with applicable Grid Code. In addition, the SPV shall inject in-firm power from the Units to the grid from time to time to carry out operational/ functional test(s) prior to the Commercial Operation Date. For avoidance of doubt, it is clarified that synchronization / connection of the Project with the grid shall not to be considered as Commissioning of the Project.
6.2.6 Subsequent to grant of connectivity and after completion of each Unit in all aspects, a delay in grant of synchronization/charging permission by the STU and/or a delay in readiness of the MSEDCL/STU substation at the Delivery Point, including readiness of the power evacuation and transmission infrastructure of the STU network until Scheduled Commercial Operation Date of the Project, shall be treated as delays beyond the control of the SPV, provided that the following are established by the SPV:the
(a) A Unit including its transmission line till STU’s MSEDCL / STU‟s substation has been completed by the SPV and CEIG approval/certificate for the same has also been obtained by the SPV;
(b) The SPV has adhered to all the applicable procedures and requirements in regard to ‘„Connectivity and Synchronization’ Synchronization‟ of the Unit as notified by the MERC/STU;
(c) The SPV has complied with the complete application formalities for connectivity within the timeline as prescribed under Law; and,
(d) The SPV has complied with the complete application formalities for synchronization of the Unit at least 15 (fifteen) days prior to CODthe Commercial Operation Date.
6.2.7 In the event of any delay as set out in Article 6.2.6 hereinabove, the Units that are impacted by such delay shall be deemed to have achieved the Commercial Operation Date on the Scheduled Commercial Operation DateSCSD. Such Units shall be eligible to receive Deemed Generation in terms of Article 7.5 hereinbelow until the event of delay set out in Article 6.2.6 hereinabove is remedied by MSEDCL.
6.2.8 Decision on eligibility for deemed achievement of Commercial Operation Date and receiving Deemed Generation on account of the above factor shall be taken by MSEDCL based on supporting documents and evidence available and provided by the SPV. In case of delay in Commissioning of a Unit due to reasons beyond the reasonable control of the SPV, MSEDCL may extend the Scheduled Commercial Operation Date SCSD after examining the issue on a case-to-case basis.
Appears in 1 contract
Sources: Power Purchase Agreement