Synchronization,CommissioningandCommercialOperation Sample Clauses

Synchronization,CommissioningandCommercialOperation. 5.1.1 The SPG shall give at least thirty (30) days’ advanced preliminary writtennotice and at least fifteen (15) days’ advanced final written notice, of the date onwhichitintendsto synchronizetheSolarPowerProjecttothe Grid System. 5.1.2 Subject to Article 5.1.1, the Power Project may be synchronized by the SPG to theGrid System when it meets all the connection conditions prescribed in applicableGrid Code then in effect and otherwise meets all other Indian legal requirements for synchronization to the Grid System. 5.1.3 Thesynchronizationequipmentandallnecessaryarrangements/equipmentincl ▇▇▇▇▇ RTU for scheduling of power generated from the Project and transmissionof data to the concerned authority as per applicable regulation shall be installed bythe SPG at its generation facility of the Power Project at its own cost. The SPG shallsynchronizeitssystemwiththeGridSystemonlyaftertheapprovalofsynchro nization scheme is granted by the head of the concerned substation/ andchecking/verificationismadebytheconcernedauthoritiesofthe. 5.1.4 The SPG shall immediately after each synchronization/tripping of generator, informthesub- stationoftheGridSystemtowhichthePowerProjectiselectricallyconnected in accordance with applicable Grid Code. In addition, the SPG will injectin-firm power to grid from time to time to carry out operational/ functional test prior tocommercial operation. For avoidance of doubt, it is clarified that Synchronization /ConnectivityoftheProjectwiththegridshallnottobeconsideredasCommissioni ngoftheProject. 5.1.5 The SPG shall commission the Project within nine (9) Months from the Date ofexecution of this PPA. Declaration of COD shall be certified by the commissioningcommittee. 5.1.6 ThePartiesagreethatforthepurposeofcommencementofthesupplyofelectricity bySPGto,liquidateddamagesfordelayetc.,theScheduledCommissioningDate asdefined inthisAgreementshallbethe relevant date.

Related to Synchronization,CommissioningandCommercialOperation

  • Synchronization, Commissioning and Commercial Operation 5.1.1 The SPG shall give PGVCL at least thirty (30) days’ advanced preliminary written notice and at least fifteen (15) days’ advanced final written notice, of the date on which it intends to synchronize the Solar Power Project to the Grid System. 5.1.2 Subject to Article 5.1.1, the Power Project may be synchronized by the SPG to the Grid System when it meets all the connection conditions prescribed in applicable Grid Code then in effect and otherwise meets all other Indian legal requirements for synchronization to the Grid System. 5.1.3 The synchronization equipment and all necessary arrangements / equipment including RTU for scheduling of power generated from the Project and transmission of data to the concerned authority as per applicable regulation shall be installed by the SPG at its generation facility of the Power Project at its own cost. The SPG shall synchronize its system with the Grid System only after the approval of synchronization scheme is granted by the head of the concerned substation/ and checking/verification is made by the concerned authorities of the PGVCL. 5.1.4 The SPG shall immediately after each synchronization/tripping of generator, inform the sub-station of the Grid System to which the Power Project is electrically connected in accordance with applicable Grid Code. In addition, the SPG will inject in-firm power to grid from time to time to carry out operational/ functional test prior to commercial operation. For avoidance of doubt, it is clarified that Synchronization / Connectivity of the Project with the grid shall not to be considered as Commissioning of the Project. 5.1.5 The SPG shall commission the Project within nine (9) Months from the Date of execution of this PPA. Declaration of COD shall be certified by the commissioning committee. 5.1.6 The Parties agree that for the purpose of commencement of the supply of electricity by SPG to PGVCL, liquidated damages for delay etc., the Scheduled Commissioning Date as defined in this Agreement shall be the relevant date.

  • Synchronization The Licensor hereby grants limited synchronization rights for One (1) music video streamed online (Youtube, Vimeo, etc..) for up to 500,000 non-monetized video streams on all total sites. A separate synchronisation license will need to be purchased for distribution of video to Television, Film or Video game.

  • Commissioning Commissioning tests of the Interconnection Customer’s installed equipment shall be performed pursuant to applicable codes and standards. The ISO and Connecting Transmission Owner must be given at least five Business Days written notice, or as otherwise mutually agreed to by the Parties, of the tests and may be present to witness the commissioning tests.

  • Start-Up and Synchronization Consistent with the mutually acceptable procedures of the Developer and Connecting Transmission Owner, the Developer is responsible for the proper synchronization of the Large Generating Facility to the New York State Transmission System in accordance with NYISO and Connecting Transmission Owner procedures and requirements.