Common use of Task Order Clause in Contracts

Task Order. The Contractor submits a Task Order programme to the Service Manager within 2 days of receiving the Task Order

Appears in 24 contracts

Sources: Nec3 Term Service Contract (Tsc3), Nec3 Term Service Contract (Tsc3), Nec3 Term Service Contract (Tsc3)

Task Order. The Contractor submits a Task Order programme to the Service Manager within 2 5 days of receiving the Task Order

Appears in 9 contracts

Sources: Nec 3: Term Service Contract (Tsc), Nec 3: Term Service Contract (Tsc), Nec 3: Term Service Contract (Tsc)

Task Order. The Contractor submits a Task Order programme to the Service Manager within 2 days One (1) week of receiving the Task Order

Appears in 6 contracts

Sources: Nec3 Term Service Contract (Tsc3), Nec3 Term Service Contract (Tsc3), Nec3 Term Service Contract (Tsc3)

Task Order. The Contractor submits a Task Order programme to the Service Manager within 2 3 days of receiving the Task Order

Appears in 5 contracts

Sources: Nec3 Term Service Contract (Tsc3), Nec3 Term Service Contract, Nec3 Term Service Contract

Task Order. The Contractor submits a Task Order programme to the Service Manager within 2 Three (3) days of receiving the Task Order

Appears in 5 contracts

Sources: Nec3 Term Service Contract, Nec3 Term Service Contract, Nec3 Term Service Contract

Task Order. The Contractor submits a Task Order programme to the Service Manager within 2 [●] days of receiving the Task Order

Appears in 5 contracts

Sources: Nec3 Term Service Contract, Nec3 Term Service Contract (Tsc3), Nec3 Term Service Contract

Task Order. The Contractor submits a Task Order programme to the Service Manager within 2 7 days of receiving the Task Order

Appears in 3 contracts

Sources: Nec3 Term Service Contract, Nec3 Term Service Contract (Tsc3), Nec3 Term Service Contract

Task Order. The Contractor submits a Task Order programme to the Service Manager within 2 [7] days of receiving the Task Order

Appears in 2 contracts

Sources: Nec3 Term Service Contract, Nec3 Term Service Contract (Tsc3)

Task Order. The Contractor submits a Task Order programme to the Service Manager within 2 days One (1) day of receiving the Task Order

Appears in 2 contracts

Sources: Nec3 Term Service Contract (Tsc3), Nec3 Term Service Contract (Tsc3)

Task Order. The Contractor submits a Task Order programme to the Service Manager within 2 14 (fourteen) days of receiving the Task Order

Appears in 2 contracts

Sources: Nec3 Term Service Contract (Tsc3), Nec3 Term Service Contract (Tsc3)

Task Order. The Contractor submits a Task Order programme to the Service Manager within 2 14 days of receiving the Task Order

Appears in 2 contracts

Sources: Nec3 Term Service Contract (Tsc3), Nec3 Term Service Contract

Task Order. The Contractor submits a Task Order programme to the Service Manager within 2 Two (2) days of receiving the Task Order

Appears in 2 contracts

Sources: Nec3 Term Service Contract (Tsc3), Nec3 Term Service Contract (Tsc3)

Task Order. The Contractor submits a Task Order programme to the Service Manager within 2 - 5 days of receiving the Task Order

Appears in 1 contract

Sources: Nec3 Term Service Contract (Tsc3)

Task Order. The Contractor submits a Task Order programme to the Service Manager within 2 days One week of receiving the Task Order

Appears in 1 contract

Sources: Nec3 Term Service Contract

Task Order. The Contractor submits a Task Order programme to the Service Manager within 2 4 days of receiving the Task Order

Appears in 1 contract

Sources: Nec3 Term Service Contract

Task Order. The Contractor submits a Task Order programme to the Service Manager within 2 days of receiving the Task Order

Appears in 1 contract

Sources: Nec3 Term Service Contract (Tsc3)

Task Order. The Contractor submits a Task Order programme to the Service Manager within 2 (two) days of receiving the Task Order.

Appears in 1 contract

Sources: Nec3 Term Service Contract (Tsc3)

Task Order. X19.5 The Contractor submits a Task Order programme to the Service Manager within 2 [25] days of receiving the Task Order

Appears in 1 contract

Sources: Nec3 Term Service Contract (Tsc3)

Task Order. The Contractor submits a Task Order programme to the Service Manager within 2 days One (1) hour of receiving the Task Order

Appears in 1 contract

Sources: Nec3 Term Service Contract

Task Order. The Contractor submits a Task Order programme to the Service Manager within 2 days of receiving 8 hours or as agreed between the Task Orderparties

Appears in 1 contract

Sources: Nec3 Term Service Contract

Task Order. The Contractor submits a Task Order programme to the Service Manager within 2 10 days of receiving the Task Order

Appears in 1 contract

Sources: Nec3 Term Service Contract

Task Order. The Contractor submits a Task Order 7 business days of receiving the Task Order programme to the Service Manager within 2 days of receiving the Task Orderwithin

Appears in 1 contract

Sources: Nec3 Term Service Contract

Task Order. The Contractor submits a Task Order programme to the Service Manager within 2 days weeks of receiving the Task Orderscope receipt

Appears in 1 contract

Sources: Nec3 Term Service Contract (Tsc3)

Task Order. The Contractor Tenderer submits a Task Order programme to the Service Manager within 2 days of receiving the Task Order

Appears in 1 contract

Sources: Nec3 Term Service Contract (Tsc3)

Task Order. The Contractor submits a Task Order 3 days of receiving the Task Order programme to the Service Manager within 2 days of receiving the Task Orderwithin

Appears in 1 contract

Sources: Nec3 Term Services Contract (Tsc)

Task Order. The Contractor submits a Task Order programme to the Service Manager within 2 [●] days 48 hours of receiving the Task Order

Appears in 1 contract

Sources: Nec3 Term Service Contract (Tsc3)

Task Order. The Contractor submits a Task Order programme to the Service Manager within 2 Two working days of receiving the Task Order

Appears in 1 contract

Sources: Nec3 Term Service Contract (Tsc3)

Task Order. The Contractor submits a Task Order programme to the Service Manager within 2 days of receiving the Task Orderprogramme

Appears in 1 contract

Sources: Nec3 Term Service Contract

Task Order. The Contractor submits a Task Order programme to the Service Manager within 2 [5] days of receiving the Task Order

Appears in 1 contract

Sources: Nec3 Term Service Contract

Task Order. The Contractor submits a Task Order programme to the Service Manager within 2 days of receiving the Task OrderOrder within

Appears in 1 contract

Sources: Nec3 Term Service Contract

Task Order. The Contractor submits a Task Order programme to the Service Manager within 2 days weeks of receiving the Task Order

Appears in 1 contract

Sources: Nec3 Term Service Contract (Tsc3)

Task Order. The Contractor submits a Task Order programme to the Service Manager within 2 days of receiving 6 hours or as agreed between the Task Orderparties

Appears in 1 contract

Sources: Nec3 Term Service Contract