Common use of Termination by the Construction Manager Clause in Contracts

Termination by the Construction Manager. 14.1.1 The Construction Manager may terminate the Contract if the Work is stopped for a period of sixty (60) consecutive days through no act or fault of the Construction Manager or a Subcontractor, Sub-subcontractor or their agents or employees or any other persons or entities performing portions of the Work under direct or indirect contract with the Construction Manager, for any of the following reasons: .1 issuance of an order of a court or other public authority having jurisdiction which requires all Work to be stopped; .2 an act of government, such as a declaration of national emergency, which requires all Work to be stopped; .3 because the Architect has not issued a Certificate for Payment and has not notified the Construction Manager of the reason for withholding certification as provided in Subparagraph 9.4.1, or because the Owner has not made payment on a Certificate for Payment within the time stated in the Contract Documents. 14.1.2 The Construction Manager may terminate the Contract if, through no act or fault of the Construction Manager or a Subcontractor, Sub-sub-contractor or their agents or employees or any other persons performing portions of the Work under direct or indirect contract with the Construction Manager, repeated suspensions, delays or interruptions of the entire Work by the Owner as described in Paragraph 14.3 constitute in the aggregate more than 100 percent of the total number of days scheduled for completion, or 120 days in any 365-day period, whichever is less. 14.1.3 If one of the reasons described in Subparagraph 14.1.1 or 14.1.2 exists, the Construction Manager may, upon seven (7) days' written notice to the Development Manager and Architect, terminate the Contract and recover from the Owner payment for Work executed and for proven loss with respect to materials, equipment, tools, and construction equipment and machinery, including an equitable portion of Construction Manager's Fee less amounts necessary for Owner to complete any corrective Work and outstanding disputed Work. 14.1.4 If the Work is stopped for a period of 90 consecutive days through no act or fault of the Construction Manager or a Subcontractor or their agents or employees or any other persons performing portions of the Work under contract with the Construction Manager because the Owner has persistently failed to fulfill the Owner's obligations under the Contract Documents with respect to matters important to the progress of the Work, the Construction Manager may, upon seven (7) additional days' written notice to the Development Manager and the Architect, terminate the Contract and recover from the Owner as provided in Subparagraph 14.1.3.

Appears in 1 contract

Sources: Agreement Between Owner and Architect (Chukchansi Economic Development Authority)

Termination by the Construction Manager. 14.1.1 The Construction Manager may terminate the Contract if the Work is stopped for a period of sixty (60) consecutive days through no act or fault of the Construction Manager or a Subcontractor, Sub-subcontractor or their agents or employees or any other persons or entities performing portions of the Work under direct or indirect contract with the Construction Manager, for any of the following reasons: .1 1. issuance of an order of a court or other public authority having jurisdiction which requires all Work to be stopped; .2 2. an act of government, such as a declaration of national emergency, which requires all Work to be stopped; .3 3. because the Architect has not issued a Certificate for Payment and has not notified the Construction Manager of the reason for withholding certification as provided in Subparagraph 9.4.1, or because the Owner has not made payment on a Certificate for Payment within the time stated in the Contract Documents. 14.1.2 The Construction Manager may terminate the Contract if, through no act or fault of the Construction Manager or a Subcontractor, Sub-sub-contractor or their agents or employees or any other persons performing portions of the Work under direct or indirect contract with the Construction Manager, repeated suspensions, delays or interruptions of the entire Work by the Owner as described in Paragraph 14.3 constitute in the aggregate more than 100 percent of the total number of days scheduled for completion, or 120 days in any 365-day period, whichever is less. 14.1.3 If one of the reasons described in Subparagraph 14.1.1 or 14.1.2 exists, the Construction Manager may, upon seven (7) days' written notice to the Development Manager and Architect, terminate the Contract and recover from the Owner payment for Work executed and for proven loss with respect to materials, equipment, tools, and construction equipment and machinery, including an equitable portion of Construction Manager's Fee less amounts necessary for Owner to complete any corrective Work and outstanding disputed Work. 14.1.4 If the Work is stopped for a period of 90 consecutive days through no act or fault of the Construction Manager or a Subcontractor or their agents or employees or any other persons performing portions of the Work under contract with the Construction Manager because the Owner has persistently failed to fulfill the Owner's obligations under the Contract Documents with respect to matters important to the progress of the Work, the Construction Manager may, upon seven (7) additional days' written notice to the Development Manager and the Architect, terminate the Contract and recover from the Owner as provided in Subparagraph 14.1.3.

Appears in 1 contract

Sources: Construction Manager Agreement (Chukchansi Economic Development Authority)