Test Showing. Each SCT must demonstrate that the Storage Facility: (1) successfully started; (2) operated for at least two (2) consecutive hours at Maximum Discharging Capacity (as defined in Exhibit A); (3) operated for at least two (2) consecutive hours at Maximum Charging Capacity (as defined in Exhibit A); (4) has a Storage Capacity of an amount that is, at least, equal to the Maximum Stored Energy Level (as defined in Exhibit A); and (5) is able to deliver Discharging Energy as measured by the Storage Facility Meter for two (2) consecutive hours at a rate equal to the Maximum Discharging Capacity.
Appears in 2 contracts
Sources: Renewable Power Purchase Agreement, Renewable Power Purchase Agreement
Test Showing. Each SCT must demonstrate that the Storage Facility:
(1) successfully started;
(2) operated for at least two four (24) consecutive hours at Maximum Discharging Capacity (as defined in Exhibit A)Capacity;
(3) operated for at least two four (24) consecutive hours at Maximum Charging Capacity (as defined in Exhibit A)Capacity;
(4) has a Storage Capacity of an amount that is, at least, equal to the Maximum Stored Energy Level (as defined in Exhibit A); and
(5) is able to deliver Discharging Energy to the Delivery Point as measured by the Storage Facility Meter for two four (24) consecutive hours at a rate equal to the Maximum Discharging Capacity.
Appears in 2 contracts
Test Showing. Each SCT must demonstrate that the Storage Facility:
(1) successfully started;
(2) operated for at least two four (24) consecutive hours at Maximum Discharging Capacity (as defined in Exhibit A)Capacity;
(3) operated for at least two four (24) consecutive hours at Maximum Charging Capacity (as defined in Exhibit A)Capacity;
(4) is able to ramp upward and downward at the contract Ramp Rate;
(5) has a Storage Capacity of an amount that is, at least, equal to the Maximum Stored Energy Level (as defined in Exhibit A); and
(56) is able to deliver Discharging Energy to the Delivery Point as measured by the Storage Facility CAISO Approved Meter for two four (24) consecutive hours at a rate equal to the Maximum Discharging Capacity.
Appears in 1 contract
Sources: Power Purchase Agreement