Test Showing. Seller must demonstrate to SCE’s reasonable satisfaction, that the Storage Unit: (1) successfully started in [SCE Note:TBD based on storage process technology and operating restrictions set forth in Appendix 1.01]; (2) operated for at least [SCE Note:TBD based on storage process technology and operating restrictions set forth in Appendix 1.01] at Maximum Discharge; (3) operated for at least [SCE Note:TBD based on storage process technology and operating restrictions set forth in Appendix 1.01] at Maximum Charge; (4) has a Storage Capacity of an amount that is, at least, equal to the Maximum Storage Level; and (5) Can deliver energy to the Point of Interconnection for four (4) consecutive hours at a rate equal to the [SCE Note: for a two hour product “RA Contract Capacity”; for a four hour product “Contract Capacity”] (as established under PART III.E. of this Appendix 7).